How are capacity requirements determined?
Capacity requirements are determined by using the control key of an activity. The control key is an object that defines various control parameters for an activity, such as scheduling type, confirmation type, costing relevance, or capacity requirements determination. The capacity requirements determination indicator in the control key specifies whether capacity requirements are calculated for an activity based on its work or duration. The capacity requirements are then used for capacity planning and leveling. Reference: https://help.sap.com/docs/SAP_S4HANA_ON-PREMISE/4dd8cb7b1c484b4b93af84d00f60fdb8/0673b65334e6b54ce10000000a174cb4.html