SAP Exam C_TS410_2504 Topic 1 Question 2 Discussion

Actual exam question for SAP's C_TS410_2504 exam
Question #: 2
Topic #: 1
[All C_TS410_2504 Questions]

What function commits funds assigned to the budget of a WBS element?

Show Suggested Answer Hide Answer
Suggested Answer: A

Availability Control (A) is the function that commits funds assigned to the budget of a WBS (Work Breakdown Structure) element. It monitors budget consumption and can issue warnings or prevent further postings when budget limits are exceeded, ensuring that project spending stays within approved budgets. Reference = SAP Project System (PS) documentation and financial controls guides.


Contribute your Thoughts:

Currently there are no comments in this discussion, be the first to comment!


Save Cancel
az-700  pass4success  az-104  200-301  200-201  cissp  350-401  350-201  350-501  350-601  350-801  350-901  az-720  az-305  pl-300  

Warning: Cannot modify header information - headers already sent by (output started at /pass.php:70) in /pass.php on line 77