SAP Exam C_STC_2405 Topic 4 Question 14 Discussion

Actual exam question for SAP's C_STC_2405 exam
Question #: 14
Topic #: 4
[All C_STC_2405 Questions]

A project-specific deliverable is not part of the SAP Activate roadmap. How can you manage all tasks that are related to that deliverable?

Show Suggested Answer Hide Answer
Suggested Answer: B

When a project-specific deliverable is not included in the standard SAP Activate roadmap, you can manage it by creating a custom deliverable in SAP Cloud ALM. This allows for tracking tasks and milestones specific to that deliverable within the project.


SAP Cloud ALM Custom Deliverable Guide

SAP Help Portal on SAP Activate Roadmap Customization

Contribute your Thoughts:

Kent
13 hours ago
I think we should go with option B, creating a custom deliverable.
upvoted 0 times
...
Cherilyn
5 days ago
Haha, I bet the SAP developers are just sitting around the office, cackling as they leave out random deliverables from the roadmap. Option B is the only way to handle that!
upvoted 0 times
...
Keshia
8 days ago
Option B is the way to go. I can't imagine the SAP Activate roadmap would have every possible deliverable, so a custom one is necessary.
upvoted 0 times
...
Nida
11 days ago
I think the correct answer is B. Creating a custom deliverable seems like the way to go to manage a project-specific deliverable outside the SAP Activate roadmap.
upvoted 0 times
...

Save Cancel
az-700  pass4success  az-104  200-301  200-201  cissp  350-401  350-201  350-501  350-601  350-801  350-901  az-720  az-305  pl-300  

Warning: Cannot modify header information - headers already sent by (output started at /pass.php:70) in /pass.php on line 77