SAP Exam C_S4TM_2023 Topic 5 Question 18 Discussion

Actual exam question for SAP's C_S4TM_2023 exam
Question #: 18
Topic #: 5
[All C_S4TM_2023 Questions]

You have flagged "GIS quality" for your means of transport, LORRY, to calculate distances and durations accurately based on GIS (geographical-information-system). In which of the following apps/customizing tasks can you define durations that impact the scheduling of a freight order using means of transport LORRY?

Note: There are 2 correct answers to this question.

Show Suggested Answer Hide Answer
Suggested Answer: B, D

Contribute your Thoughts:

Lettie
4 months ago
Oh man, can you imagine trying to schedule a freight order without using the GIS features? Talk about a logistical nightmare!
upvoted 0 times
...
Eura
4 months ago
Well, well, well... looks like we need to keep an eye on those GIS-powered lorries! I'm betting on B) Define scheduling settings and D) Define transportation lane.
upvoted 0 times
Lon
4 months ago
I agree, those options seem to be the most relevant for defining durations that impact scheduling.
upvoted 0 times
...
Laurel
4 months ago
I think you're right, B) Define scheduling settings and D) Define transportation lane are the correct options.
upvoted 0 times
...
...
Shelton
5 months ago
This is a tricky one, but I'm going to go with B) Define scheduling settings and C) Edit schedule. Nailed it!
upvoted 0 times
...
Helene
5 months ago
Hmm, I'm going with B) Define scheduling settings and D) Define transportation lane. Wouldn't want to mess up the freight order scheduling, right?
upvoted 0 times
Nieves
3 months ago
True, B) Define scheduling settings is essential for setting up the scheduling parameters.
upvoted 0 times
...
Crissy
4 months ago
Definitely, but I think D) Define transportation lane is crucial for calculating distances accurately.
upvoted 0 times
...
Harris
4 months ago
I agree, C) Edit schedule can also impact the scheduling of a freight order.
upvoted 0 times
...
Janessa
4 months ago
I think A) Maintain scheduling constraints is also important for accurate scheduling.
upvoted 0 times
...
...
Rosendo
5 months ago
I'm not sure about the answers. Can someone explain why A) Maintain scheduling constraints and B) Define scheduling settings are the correct choices?
upvoted 0 times
...
Elizabeth
5 months ago
I agree with Xuan. Those options make sense for defining durations that impact scheduling of a freight order.
upvoted 0 times
...
Xuan
5 months ago
I think the correct answers are A) Maintain scheduling constraints and B) Define scheduling settings.
upvoted 0 times
...
Donte
5 months ago
I think the correct answers are B) Define scheduling settings and C) Edit schedule. Gotta love those GIS-enabled lorries!
upvoted 0 times
Cordell
4 months ago
It's great to have that level of accuracy and efficiency in transportation planning.
upvoted 0 times
...
Barabara
5 months ago
I always make sure to define scheduling settings and edit the schedule for my GIS quality lorry.
upvoted 0 times
...
Nohemi
5 months ago
Yes, those are the correct answers. GIS-enabled lorries make scheduling so much easier.
upvoted 0 times
...
Cornell
5 months ago
I believe the correct answers are B) Define scheduling settings and C) Edit schedule.
upvoted 0 times
...
...

Save Cancel
az-700  pass4success  az-104  200-301  200-201  cissp  350-401  350-201  350-501  350-601  350-801  350-901  az-720  az-305  pl-300  

Warning: Cannot modify header information - headers already sent by (output started at /pass.php:70) in /pass.php on line 77