SAP Exam C_S4PPM_2021 Topic 6 Question 49 Discussion

Actual exam question for SAP's C_S4PPM_2021 exam
Question #: 49
Topic #: 6
[All C_S4PPM_2021 Questions]

What must you configure to view portfolio item data in project management projects?

Show Suggested Answer Hide Answer
Suggested Answer: D

Contribute your Thoughts:

Marjory
1 days ago
I think the answer is A) Set the project management flag to active in customizing for the linking item type.
upvoted 0 times
...
Lanie
5 days ago
Hmm, I'm not sure about that. I was thinking it might be option B - setting the business content data source for portfolio management in customizing.
upvoted 0 times
...
Farrah
11 days ago
I think it's option D. The portfolio management flag needs to be active for the project type in order to view portfolio item data.
upvoted 0 times
Nicolette
3 days ago
I believe it's option D. The portfolio management flag must be active for the project type.
upvoted 0 times
...
...