SAP Exam C_S4PPM_2021 Topic 2 Question 41 Discussion

Actual exam question for SAP's C_S4PPM_2021 exam
Question #: 41
Topic #: 2
[All C_S4PPM_2021 Questions]

No upcoming milestone are shown in the my projects SAP Fiori app.

What are the reasons for this?

NOTE: There are 2 correct answers to this question

Show Suggested Answer Hide Answer
Suggested Answer: B, C

Contribute your Thoughts:

Na
2 months ago
Seriously, who designs these apps? They must be using a magic 8-ball or something.
upvoted 0 times
Demetra
19 days ago
C) Project is not released
upvoted 0 times
...
Mitsue
30 days ago
B) Milestone is not identified as mandatory
upvoted 0 times
...
Candra
1 months ago
A) You are not defined as the project Responsible
upvoted 0 times
...
...
Frank
2 months ago
Oh, I know this one! Milestone not identified as critical. Classic SAP move right there.
upvoted 0 times
...
Elfriede
2 months ago
Project not released, huh? I guess the dev team is still working on it. Patience is a virtue, they say.
upvoted 0 times
Josephine
25 days ago
C) Project is not released
upvoted 0 times
...
Kenneth
26 days ago
A) You are not defined as the project Responsible
upvoted 0 times
...
...
Sharmaine
2 months ago
I think the project not being released could also be a reason for the upcoming milestones not showing up.
upvoted 0 times
...
Noah
2 months ago
Ha! Milestone not identified as mandatory? That's a classic Fiori app problem. I feel your pain.
upvoted 0 times
...
Dalene
2 months ago
Hmm, looks like the project responsible is the key here. I bet that's the issue.
upvoted 0 times
Tiera
17 days ago
D) Milestone is not identified as critical
upvoted 0 times
...
Lisha
26 days ago
C) Project is not released
upvoted 0 times
...
Ligia
28 days ago
B) Milestone is not identified as mandatory
upvoted 0 times
...
Zoila
1 months ago
A) You are not defined as the project Responsible
upvoted 0 times
...
...
Brett
2 months ago
I agree with Galen. Another reason could be that the milestone is not identified as mandatory.
upvoted 0 times
...
Galen
2 months ago
I think the reason could be that I am not defined as the project Responsible.
upvoted 0 times
...