Question #: 77
Topic #: 2
[All PRINCE2-Foundation Questions]

Identify the missing words in the following sentence.

The 'managing product delivery' process provides a controlled link between [ ? ] and a project manager.

Show Suggested Answer Hide Answer
Suggested Answer: D

Contribute your Thoughts:

Dick
2 days ago
I think the missing word is team manager.
upvoted 0 times
...