Independence Day Deal! Unlock 25% OFF Today – Limited-Time Offer - Ends In 00:00:00 Coupon code: SAVE25
Welcome to Pass4Success

- Free Preparation Discussions

PRINCE2 Exam PRINCE2-Practitioner Topic 4 Question 81 Discussion

Actual exam question for PRINCE2's PRINCE2-Practitioner exam
Question #: 81
Topic #: 4
[All PRINCE2-Practitioner Questions]

Scenario

Product Summary

A list of customers will be collated. This will use existing information from the Accounts department about current customers, and existing information from the Marketing department about prospective customers.

Using the tariff of mailing costs available from the Post Office, a production cost forecast will be produced to allow the CEO and the Marketing Director to decide whether to continue with the project. If they decide to continue, they will give the approval to launch the internal label design competition. Competition rules will be required to communicate details of the competition to the staff. The chosen label design will then be selected from the competition entries.

The photos for the calendar must be based on existing photo design ideas available from the Marketing department. The selected photos will be chosen from these. Monthly calendar displays will be created to show the required layout of each page.

Product Breakdown Structure (contains errors)

Extract from Stage Plan for stage 3.

(All entries are true statements but may not be shown under the correct heading or in the correct document).

Using the Project Scenario and the Extract from Stage Plan for stage 3 provided as additional intonation for this question in the Scenario Booklet, answer the following 5 questions.

The Stage Plan for stage 3 has been produced.

The Engineering Manager insists that there are to be no interruptions to operations whilst photographs are being taken of the engineering staff performing their everyday duties and operating machinery. Two weeks ago the professional photographer produced the photo session schedule based on the operational staff schedule. The operational staff schedule is produced weekly and maintained by the Engineering Manager.

None of the 500 change budget has been used to date and this is available for the stage.

Which 2 statements apply to the External dependencies section?

Show Suggested Answer Hide Answer
Suggested Answer: A

Contribute your Thoughts:

Olive
1 months ago
Wait, they're taking photos of the engineering staff 'performing their everyday duties'? I hope the photographer is ready for some serious 'action shots' of people staring at computer screens and drinking coffee!
upvoted 0 times
Eleonora
19 days ago
Haha, that would make for some interesting calendar photos!
upvoted 0 times
...
...
Shawnda
1 months ago
Alright, let's tackle this step-by-step. I reckon B and D are the way to go, but I'm still a bit unsure about the whole scenario.
upvoted 0 times
...
Stephania
1 months ago
Haha, the Engineering Manager is really adamant about no interruptions during the photo shoot. I hope the photographer has some sneaky tricks up their sleeve!
upvoted 0 times
Linn
6 days ago
C: Maybe the photographer will have to be really quick and sneaky to capture the staff in action.
upvoted 0 times
...
Joseph
9 days ago
B: Yeah, I wonder how the photographer will manage to get the shots without any interruptions.
upvoted 0 times
...
Daron
15 days ago
A: The Engineering Manager seems very strict about the photo shoot.
upvoted 0 times
...
...
Lacey
1 months ago
The external dependencies section seems to be the key here. Entries 5 and 6 seem like they don't belong there, so I'd go with B and D.
upvoted 0 times
...
Cecily
2 months ago
This question is quite tricky. I'm not sure if I understand the scenario fully, but I think the correct answers are B and D.
upvoted 0 times
Merlyn
15 days ago
Let's go with B and see how it goes.
upvoted 0 times
...
Jennifer
21 days ago
I'm not sure about D, but B definitely makes sense.
upvoted 0 times
...
Margurite
29 days ago
I agree, those seem to be the most logical choices.
upvoted 0 times
...
Buddy
2 months ago
I think the correct answers are B and D.
upvoted 0 times
...
...
Justine
2 months ago
I think we should also delete entry 7 as it should be in the Product Description.
upvoted 0 times
...
Dewitt
2 months ago
I agree with Dyan. Moving entry 5 to Plan prerequisites makes sense.
upvoted 0 times
...
Dyan
2 months ago
I think we should delete entry 5 because the new company logo is being delivered separately.
upvoted 0 times
...

Save Cancel
az-700  pass4success  az-104  200-301  200-201  cissp  350-401  350-201  350-501  350-601  350-801  350-901  az-720  az-305  pl-300  

Warning: Cannot modify header information - headers already sent by (output started at /pass.php:70) in /pass.php on line 77