Deal of The Day! Hurry Up, Grab the Special Discount - Save 25% - Ends In 00:00:00 Coupon code: SAVE25
Welcome to Pass4Success

- Free Preparation Discussions

PRINCE2 Exam PRINCE2-Practitioner Topic 4 Question 50 Discussion

Actual exam question for PRINCE2's PRINCE2-Practitioner exam
Question #: 50
Topic #: 4
[All PRINCE2-Practitioner Questions]

It is now late October and the project is in stage 3. The label design competition has been held and the photos of the staff have been taken. The CEO and Marketing Director still need to choose the winning label design and the 12 photos for the calendar. However, the Executive has learned that two competitors are issuing calendars to MNO's customers by the middle of November. After analyzing the impact of this Issue, one of the options the Project Manager has presented to the Project Board is to close the project prematurely.

There are a number of key facts relating to this project that would need to be recorded if the project Y-e to be closed now.

Which product should register that the risk of a competitor producing a calendar at the same time was identified at the beginning of the project but the assessment of this risk appears to have been poor?

Show Suggested Answer Hide Answer
Suggested Answer: B

Contribute your Thoughts:

Dick
13 days ago
Closing the project prematurely might be the best option if the risk was not properly assessed and recorded in the Risk Register.
upvoted 0 times
...
Erin
20 days ago
I agree with Jacob, the poor assessment of this risk should have been documented in the Risk Register.
upvoted 0 times
...
Jacob
22 days ago
I think the risk of a competitor producing a calendar should have been recorded in the Risk Register.
upvoted 0 times
...

Save Cancel
az-700  pass4success  az-104  200-301  200-201  cissp  350-401  350-201  350-501  350-601  350-801  350-901  az-720  az-305  pl-300  

Warning: Cannot modify header information - headers already sent by (output started at /pass.php:70) in /pass.php on line 77