PRINCE2 Exam PRINCE2-Practitioner Topic 3 Question 86 Discussion

Actual exam question for PRINCE2's PRINCE2-Practitioner exam
Question #: 86
Topic #: 3
[All PRINCE2-Practitioner Questions]

It is now late October and the project is in stage 3. The label design competition has been held and the photos of the staff have been taken. The CEO and Marketing Director still need to choose the winning label design and the 12 photos for the calendar. However, the Executive has learned that two competitors are issuing calendars to MNO's customers by the middle of November. After analyzing the impact of this Issue, one of the options the Project Manager has presented to the Project Board is to close the project prematurely.

There are a number of key facts relating to this project that would need to be recorded if the project Y-e to be closed now.

Which product should show that if anybody has any remaining resource costs to be charged to the project, they should ensure this is done by 10 November?

Show Suggested Answer Hide Answer
Suggested Answer: D

Contribute your Thoughts:

Cristen
1 months ago
Follow-on action recommendations? Pfft, like anyone's going to care about that when the project's shutting down early. Just give me the End Project Report and let's move on.
upvoted 0 times
Kip
8 days ago
I'm with you, let's prioritize the End Project Report and get everything finalized.
upvoted 0 times
...
Nieves
10 days ago
I think we should still consider the Follow-on action recommendations, they could be useful for future projects.
upvoted 0 times
...
Martha
1 months ago
I agree, let's just focus on the End Project Report and wrap this up quickly.
upvoted 0 times
...
...
Arthur
2 months ago
Benefits Review Plan? Are you kidding me? That's for when the project is a success, not a premature closure! End Project Report all the way.
upvoted 0 times
Brandon
8 days ago
Let's make sure to complete the End Project Report by 10 November to capture all remaining resource costs before closing the project.
upvoted 0 times
...
Stefania
10 days ago
I agree, End Project Report is the best option in this situation. It will help us wrap things up properly.
upvoted 0 times
...
Trevor
12 days ago
End Project Report is the way to go. It will document all the key facts if we close the project early.
upvoted 0 times
...
...
Paola
2 months ago
End Project Report, for sure. It's like the project's obituary - got to make sure it's detailed and accurate. No 'fake news' allowed here!
upvoted 0 times
...
Lorrine
2 months ago
End Project Report? Definitely, that's where the key facts about the project closure would be recorded. Can't leave anything to chance, you know.
upvoted 0 times
...
Queenie
2 months ago
I disagree. I think we should consider option C) Follow-on action recommendations to address the impact of competitors issuing calendars early. It could help us come up with a plan to mitigate the situation.
upvoted 0 times
...
Kendra
2 months ago
I agree with Alecia. The End Project Report will help us document all the key facts and ensure any remaining resource costs are charged by 10 November.
upvoted 0 times
...
Alecia
2 months ago
I think we should go with option B) End Project Report.
upvoted 0 times
...

Save Cancel