Deal of The Day! Hurry Up, Grab the Special Discount - Save 25% - Ends In 00:00:00 Coupon code: SAVE25
Welcome to Pass4Success

- Free Preparation Discussions

PRINCE2 Exam PRINCE2-Practitioner Topic 3 Question 58 Discussion

Actual exam question for PRINCE2's PRINCE2-Practitioner exam
Question #: 58
Topic #: 3
[All PRINCE2-Practitioner Questions]

It is now late October and the project is in stage 3. The label design competition has been held and the photos of the staff have been taken. The CEO and Marketing Director still need to choose the winning label design and the 12 photos for the calendar. However, the Executive has learned that two competitors are issuing calendars to MNO's customers by the middle of November. After analyzing the impact of this Issue, one of the options the Project Manager has presented to the Project Board is to close the project prematurely.

There are a number of key facts relating to this project that would need to be recorded if the project Y-e to be closed now.

Which product should show that the staff photo sessions were disruptive to the Engineering Department as they had been scheduled during peak work times without consultation with the Engineering Manager?

Show Suggested Answer Hide Answer
Suggested Answer: A

Contribute your Thoughts:

Herman
1 days ago
Definitely the Lessons Report. Gotta document that disruption to the Engineering Department - it's the only way the organization can improve. Although, I have to wonder if the CEO and Marketing Director were trying to sabotage the engineers. Maybe they just wanted to see the look on the Engineering Manager's face when they scheduled the photos!
upvoted 0 times
...
Nada
10 days ago
I agree, the Lessons Report is the best choice here. It's important to capture and learn from these kinds of project challenges, otherwise we're doomed to repeat them. Though I have to say, scheduling photo sessions during peak engineering work times? That's a whole new level of workplace comedy!
upvoted 0 times
...
Pansy
11 days ago
The Lessons Report would be the appropriate product to document the disruptive impact of the staff photo sessions on the Engineering Department. This can help the organization learn from this experience and avoid similar issues in future projects.
upvoted 0 times
...
Lucille
16 days ago
I believe the Lessons Report would be the best option to record the disruptive staff photo sessions.
upvoted 0 times
...
Keneth
22 days ago
I agree with Glory, it's important to document that key fact if the project is to be closed prematurely.
upvoted 0 times
...
Glory
25 days ago
I think the product should show that the staff photo sessions were disruptive to the Engineering Department.
upvoted 0 times
...

Save Cancel
az-700  pass4success  az-104  200-301  200-201  cissp  350-401  350-201  350-501  350-601  350-801  350-901  az-720  az-305  pl-300  

Warning: Cannot modify header information - headers already sent by (output started at /pass.php:70) in /pass.php on line 77