Question #: 55
Topic #: 3
[All PRINCE2-Practitioner Questions]

Scenario

Additional Information

Product Description

Quality notes from the Daily Log

The Director of Information Technology Division (DIT) has been asked to ensure that any changes to the outsourced staff employment contracts adhere to employment law. The DIT will review future job descriptions of the transferred staff before the final contract is signed with the selected service provider.

The service level agreement between MFH and the selected service provider will specify the type and quality of service required. The selected service provider must follow the industry standards for providing outsourced services.

MFH has a quality management system which contains a document control procedure for all its documentation, however this does not include change management.

All project documents will be subject to a quality review. Nominated products will require a formal approval record signed-off by the quality review chair.

Extract from the draft Quality Management Strategy (may contain errors)

Introduction

1. This document defines the approach to be taken to achieve the required quality levels during the project.

2. The Project Board will have overall responsibility for the Quality Management Strategy.

3. Project Assurance will provide assurance on the implementation of the Quality Management Strategy.

Quality management procedure - Quality standards

4. The selected service provider will operate to industry standards for providing outsourced services.

5. MFH document standards will be used.

Records

6. A Quality Register will be maintained to record the planned quality events and the actual results from the quality activities.

7. Configuration Item Records will be maintained for each product to describe its status, version and variant.

8. Approval records for products that require them will be stored in the quality database.

Roles and responsibilities

9. The DIT will check that the employment contracts for outsourced staff adhere to employment law.

10. Team Managers will provide details of quality checks that have been carried out.

11. Team Managers will ensure that the Quality Register is updated with the names of team members who are involved in the review process.

12. The Senior User will review the Product Descriptions of the products to be produced by the selected service provider to ensure that they can be achieved.

The service level agreement looks like any other MFH document.

Show Suggested Answer Hide Answer
Suggested Answer: C

Contribute your Thoughts:

Kati
3 hours ago
Hold up, the quality management strategy mentions a document control procedure, but no change management. Shouldn't we raise an issue to address that gap? I'm leaning towards option B.
upvoted 0 times
...
Paul
2 days ago
The question seems straightforward. The service level agreement needs to adhere to industry standards, and the DIT needs to review the employment contracts. I think option D is the correct answer here.
upvoted 0 times
...
Marg
13 days ago
I disagree, I think we should raise an issue (off-specification) as option B to address the error in the service level agreement.
upvoted 0 times
...
Huey
14 days ago
I agree with Arthur, it's important to ensure the quality of service by obtaining agreement from the Director of Facilities Division.
upvoted 0 times
...
Arthur
16 days ago
I think we should go with option A and redesign the service level agreement.
upvoted 0 times
...
Marti
18 days ago
I believe obtaining agreement from the Director of Facilities Division to redesign the service level agreement is the best course of action to maintain quality.
upvoted 0 times
...
Lera
22 days ago
I agree with Odette, we need to ensure that the service level agreement meets the required quality standards.
upvoted 0 times
...
Odette
24 days ago
I think we should raise an issue (off-specification) because this error could impact the quality of the project.
upvoted 0 times
...

Save Cancel
az-700  pass4success  az-104  200-301  200-201  cissp  350-401  350-201  350-501  350-601  350-801  350-901  az-720  az-305  pl-300  

Warning: Cannot modify header information - headers already sent by (output started at /pass.php:70) in /pass.php on line 77