PRINCE2 Exam PRINCE2-Practitioner Topic 2 Question 66 Discussion

Actual exam question for PRINCE2's PRINCE2-Practitioner exam
Question #: 66
Topic #: 2
[All PRINCE2-Practitioner Questions]

Scenario

Additional Information

Chief Executive Officer (CEO): He started the company 25 years ago and knows his job very well. He injured his leg two years ago which has restricted his visits to the engineering area. As CEO he has an overall perspective of the business strategic requirements and the authority to commit resources as required.

Marketing Director: She has been with the company for three years, following a successful career with a publicity company. She has the ability to represent the needs of the business, particularly as this is a marketing project. She has the authority to commit the annual business marketing budget, from which the project will be funded, as she sees appropriate. She will be responsible for monitoring the expected benefits of the calendar, in particular the improvement of the company's image.

Engineering Manager: He has been responsible for many engineering innovations in the company and is still as keen and energetic as the day he started. VVhilst he will not be part of the project team, his staff will feature in the photos for the promotional calendar.

Central Records: This group of five staff looks after all company records and document control. They now maintain all project files.

Bright Lights: This is the local office supplies company. It supplies all the stationery and office equipment needs of the company and will supply the stationery for this project.

Portraits ltd: This is a professional photographic company with a number of excellent photographers and a history of successful work. This company has been selected to take the photos for the company calendar. It has yet to be decided which of the photographers to use.

Which 2 statements explain why the Sales Manager should be appointed as User Assurance for this project?

Show Suggested Answer Hide Answer
Suggested Answer: B

Contribute your Thoughts:

Yvonne
1 months ago
E is an interesting option, but I agree that B and C are the best choices. The Sales Manager can really bridge the gap between sales and marketing with this project.
upvoted 0 times
Micaela
4 days ago
Having someone who can bridge the gap between sales and marketing is crucial for the success of this project.
upvoted 0 times
...
Doyle
9 days ago
I agree, the Sales Manager can provide valuable insights on the potential impact on sales and advise on stakeholder engagement.
upvoted 0 times
...
Marion
19 days ago
I think B and C are definitely the best choices for the Sales Manager to be appointed as User Assurance.
upvoted 0 times
...
...
Howard
2 months ago
Haha, the Sales Manager as User Assurance? Sounds like he's trying to pad his resume for that Marketing job. But B and C do make the most sense.
upvoted 0 times
...
Simona
2 months ago
I think D is a bit of a stretch. The Sales Manager shouldn't be appointed just because he wants to move to Marketing. B and C are the clear choices here.
upvoted 0 times
Shantell
1 days ago
C) He is able to advise on suitable stakeholder engagement of current and prospective customers.
upvoted 0 times
...
Pearlene
4 days ago
B) He can provide an evaluation of the potential impact the calendar will have on sales.
upvoted 0 times
...
Cassie
1 months ago
A) He joined the company last year with huge enthusiasm and is keen to increase sales.
upvoted 0 times
...
...
Noemi
2 months ago
The correct answer is B and C. The Sales Manager can provide valuable insights into how the calendar will impact sales, and can help engage stakeholders like customers.
upvoted 0 times
...
Cora
2 months ago
But what about the potential conflict between Sales and Marketing departments? The Sales Manager could help resolve that.
upvoted 0 times
...
Jesusita
2 months ago
I agree, having someone who understands the sales perspective is crucial for this project.
upvoted 0 times
...
Wei
2 months ago
I think the Sales Manager should be appointed as User Assurance because he can evaluate the impact on sales.
upvoted 0 times
...

Save Cancel