PRINCE2 Exam PRINCE2-Practitioner Topic 2 Question 40 Discussion

Actual exam question for PRINCE2's PRINCE2-Practitioner exam
Question #: 40
Topic #: 2
[All PRINCE2-Practitioner Questions]

Scenario

Product Summary

A list of customers will be collated. This will use existing information from the Accounts department about current customers, and existing information from the Marketing department about prospective customers.

Using the tariff of mailing costs available from the Post Office, a production cost forecast will be produced to allow the CEO and the Marketing Director to decide whether to continue with the project. If they decide to continue, they will give the approval to launch the internal label design competition. Competition rules will be required to communicate details of the competition to the staff. The chosen label design will then be selected from the competition entries.

The photos for the calendar must be based on existing photo design ideas available from the Marketing department. The selected photos will be chosen from these. Monthly calendar displays will be created to show the required layout of each page.

Product Breakdown Structure (contains errors)

Extract from Stage Plan for stage 3.

(All entries are true statements but may not be shown under the correct heading or in the correct document).

Using the Project Scenario and the Extract from Stage Plan for stage 3 provided as additional intonation for this question in the Scenario Booklet, answer the following 5 questions.

The Stage Plan for stage 3 has been produced.

The Engineering Manager insists that there are to be no interruptions to operations whilst photographs are being taken of the engineering staff performing their everyday duties and operating machinery. Two weeks ago the professional photographer produced the photo session schedule based on the operational staff schedule. The operational staff schedule is produced weekly and maintained by the Engineering Manager.

None of the 500 change budget has been used to date and this is available for the stage.

Which 2 statements apply to the Planning assumptions section?

Show Suggested Answer Hide Answer
Suggested Answer: A

Contribute your Thoughts:

Alyce
12 days ago
Why do you think that?
upvoted 0 times
...
Dick
12 days ago
I'm not sure about deleting entry 9. The photo session schedule should have been approved in stage 2, but it's still relevant to the planning assumptions for stage 3.
upvoted 0 times
...
Tawna
13 days ago
I disagree, I believe the correct answer is D.
upvoted 0 times
...
Berry
18 days ago
Option B makes the most sense. The label designs are indeed created outside the project, so they should be considered an external dependency.
upvoted 0 times
...
Alyce
19 days ago
I think the answer is A.
upvoted 0 times
...