PRINCE2 Exam PRINCE2-Practitioner Topic 1 Question 70 Discussion

Actual exam question for PRINCE2's PRINCE2-Practitioner exam
Question #: 70
Topic #: 1
[All PRINCE2-Practitioner Questions]

Who is responsible for committing user resources to the project?

Show Suggested Answer Hide Answer
Suggested Answer: B

Contribute your Thoughts:

An
1 months ago
I bet the Project Board just flips a coin to decide who gets the resources. Heads you win, tails you lose!
upvoted 0 times
Nobuko
2 days ago
B) Senior Supplier
upvoted 0 times
...
Kerry
18 days ago
A) Senior User
upvoted 0 times
...
...
Erick
1 months ago
If the Executive is responsible, does that mean they can just magically conjure up resources out of thin air? I don't think so!
upvoted 0 times
Melynda
4 days ago
C) Executive
upvoted 0 times
...
Mabelle
12 days ago
B) Senior Supplier
upvoted 0 times
...
Stephanie
18 days ago
A) Senior User
upvoted 0 times
...
...
Reena
1 months ago
Hold up, the Senior Supplier is the one who provides the resources, so B is the correct answer. Easy peasy!
upvoted 0 times
That's right! The Senior Supplier is responsible for providing the resources.
upvoted 0 times
...
Aliza
2 days ago
D) Project Board
upvoted 0 times
...
Shawnda
4 days ago
C) Executive
upvoted 0 times
...
Laurel
16 days ago
B) Senior Supplier
upvoted 0 times
...
Edgar
1 months ago
A) Senior User
upvoted 0 times
...
...
Cyndy
1 months ago
I'm pretty sure the Executive has the final say on resource allocation. C is the way to go!
upvoted 0 times
...
Starr
2 months ago
Nah, the Project Board is the one who approves the allocation of resources, so it's gotta be D.
upvoted 0 times
Evelynn
3 days ago
Senior User may have input, but ultimately it's the Project Board that makes the final decision.
upvoted 0 times
...
Talia
4 days ago
You're right, the Project Board ultimately approves the allocation of resources.
upvoted 0 times
...
Ellsworth
4 days ago
Yeah, the Project Board has the authority to allocate resources for the project.
upvoted 0 times
...
Claudia
8 days ago
I think you're right, the Project Board is responsible for committing user resources to the project.
upvoted 0 times
...
Justine
1 months ago
But the Senior Supplier also plays a role in committing resources.
upvoted 0 times
...
Donte
1 months ago
No, it's actually the Senior User who is responsible for that.
upvoted 0 times
...
Herman
2 months ago
I think it's the Executive who commits user resources.
upvoted 0 times
...
...
Timothy
2 months ago
I think it could also be D) Project Board, as they oversee the project as a whole.
upvoted 0 times
...
Theron
2 months ago
I agree with Lettie, Senior User is responsible for committing user resources.
upvoted 0 times
...
Alida
2 months ago
The Senior User is responsible for committing user resources to the project, so I think the answer is A.
upvoted 0 times
Leah
1 months ago
That's correct, the Senior User is the one who should be making decisions regarding user resources.
upvoted 0 times
...
Heidy
1 months ago
Yes, the Senior User plays a crucial role in allocating user resources to the project.
upvoted 0 times
...
Rosendo
1 months ago
So the answer must be A) Senior User.
upvoted 0 times
...
Katina
2 months ago
I agree, the Senior User is the one responsible for committing user resources to the project.
upvoted 0 times
...
...
Lettie
3 months ago
I think the answer is A) Senior User.
upvoted 0 times
...

Save Cancel
az-700  pass4success  az-104  200-301  200-201  cissp  350-401  350-201  350-501  350-601  350-801  350-901  az-720  az-305  pl-300  

Warning: Cannot modify header information - headers already sent by (output started at /pass.php:70) in /pass.php on line 77