PRINCE2 Exam PRINCE2-Practitioner Topic 1 Question 47 Discussion

Actual exam question for PRINCE2's PRINCE2-Practitioner exam
Question #: 47
Topic #: 1
[All PRINCE2-Practitioner Questions]

It is now late October and the project is in stage 3. The label design competition has been held and the photos of the staff have been taken. The CEO and Marketing Director still need to choose the winning label design and the 12 photos for the calendar. However, the Executive has learned that two competitors are issuing calendars to MNO's customers by the middle of November. After analyzing the impact of this Issue, one of the options the Project Manager has presented to the Project Board is to close the project prematurely.

There are a number of key facts relating to this project that would need to be recorded if the project Y-e to be closed now.

Which product should show that without the calendar the company is going to experience difficulties recovering its decline in orders, and alternative solutions are required if the company is going to recover its position?

Show Suggested Answer Hide Answer

Contribute your Thoughts:

Detra
1 days ago
Haha, the Risk Register? That's like trying to put out a fire with gasoline. We need something that actually addresses the problem, not just lists the risks.
upvoted 0 times
...
Noel
3 days ago
The Exception Report could work, but it might not provide the comprehensive overview that the End Project Report would.
upvoted 0 times
...
Michel
6 days ago
I disagree. I think we should go with option A) Benefits Review Plan to analyze the impact of not having the calendar on our orders.
upvoted 0 times
...
Adrianna
7 days ago
I agree with Lauryn. The End Project Report will help us document the key facts and reasons for closing the project prematurely.
upvoted 0 times
...
Lauryn
8 days ago
I think we should choose option C) End Project Report.
upvoted 0 times
...
Gladis
10 days ago
I'm not sure, but maybe we should also consider option A) Benefits Review Plan to assess the impact of not having the calendar on our orders.
upvoted 0 times
...
Hui
14 days ago
I agree with Vicki. The End Project Report will help us document the key facts and reasons for closing the project prematurely.
upvoted 0 times
...
Rodolfo
15 days ago
I'm not sure if the Benefits Review Plan is the right option since the focus seems to be on the challenges faced rather than the benefits achieved.
upvoted 0 times
Melda
4 days ago
A) Benefits Review Plan
upvoted 0 times
...
...
Vicki
16 days ago
I think we should choose option C) End Project Report.
upvoted 0 times
...
Vanesa
18 days ago
The End Project Report seems like the appropriate choice here. It would capture all the key facts and highlight the impact of the competitors issuing calendars early.
upvoted 0 times
...

Save Cancel
az-700  pass4success  az-104  200-301  200-201  cissp  350-401  350-201  350-501  350-601  350-801  350-901  az-720  az-305  pl-300  

Warning: Cannot modify header information - headers already sent by (output started at /pass.php:70) in /pass.php on line 77