PRINCE2 Exam PRINCE2-Foundation Topic 2 Question 81 Discussion

Actual exam question for PRINCE2's PRINCE2-Foundation exam
Question #: 81
Topic #: 2
[All PRINCE2-Foundation Questions]

Which is a purpose of the Risk theme?

Show Suggested Answer Hide Answer
Suggested Answer: B

Contribute your Thoughts:

Clarence
2 months ago
The Risk theme? More like the 'Risque' theme, amirite?
upvoted 0 times
Tequila
26 days ago
C) Establish mechanisms to control any unacceptable deviations from plan
upvoted 0 times
...
Jutta
30 days ago
D) Establish mechanisms to manage risks at the corporate or programme level of an organization
upvoted 0 times
...
Leatha
1 months ago
A) Establish a cost-effective procedure to identify, assess and control uncertainty
upvoted 0 times
...
Santos
1 months ago
C) Establish mechanisms to control any unacceptable deviations from plan
upvoted 0 times
...
Lino
1 months ago
A) Establish a cost-effective procedure to identify, assess and control uncertainty
upvoted 0 times
...
...
Chandra
2 months ago
Option B, for sure. The other choices sound more like they belong in the Governance or Change Control themes.
upvoted 0 times
...
Caprice
2 months ago
Hmm, I was thinking Option D, but now I'm not so sure. Is the Risk theme only for corporate-level risks?
upvoted 0 times
Erick
26 days ago
B) Establish a cost-effective procedure to identify, assess and control uncertainty
upvoted 0 times
...
Margot
28 days ago
The Risk theme is not only for corporate-level risks, it also includes programme-level risks.
upvoted 0 times
...
Cyndy
1 months ago
D) Establish mechanisms to manage risks at the corporate or programme level of an organization
upvoted 0 times
...
Glen
1 months ago
C) Establish mechanisms to control any unacceptable deviations from plan
upvoted 0 times
...
Malissa
2 months ago
B) Establish a cost-effective procedure to identify, assess and control uncertainty
upvoted 0 times
...
Shizue
2 months ago
A) Establish a procedure to ensure every change is agreed by the relevant authority before it takes place
upvoted 0 times
...
...
Shanice
2 months ago
I believe option B is the best answer because it helps ensure the project stays on track and within budget.
upvoted 0 times
...
Cordelia
2 months ago
I agree with Felicidad. The Risk theme is all about being proactive and cost-effective in dealing with risks.
upvoted 0 times
...
Felicidad
2 months ago
Option B seems to be the correct answer. Identifying and managing uncertainty is a core purpose of the Risk theme.
upvoted 0 times
Vesta
18 days ago
Establishing mechanisms to control risks is key in project management.
upvoted 0 times
...
Jenifer
20 days ago
Managing uncertainty is crucial for project success.
upvoted 0 times
...
Jennie
1 months ago
It's important to have a cost-effective procedure in place for risk management.
upvoted 0 times
...
Mauricio
2 months ago
I agree, option B is focused on identifying and managing uncertainty.
upvoted 0 times
...
...
Karl
2 months ago
I agree with Jimmie. Managing risks efficiently can save time and resources in the long run.
upvoted 0 times
...
Jimmie
3 months ago
I think the purpose of the Risk theme is to establish a cost-effective procedure to identify, assess and control uncertainty.
upvoted 0 times
...

Save Cancel
az-700  pass4success  az-104  200-301  200-201  cissp  350-401  350-201  350-501  350-601  350-801  350-901  az-720  az-305  pl-300  

Warning: Cannot modify header information - headers already sent by (output started at /pass.php:70) in /pass.php on line 77