What should the business case state about the minimum viable product (MVP)?

Show Suggested Answer Hide Answer
Suggested Answer: C

Contribute your Thoughts:

Rose
26 days ago
I hope the exam doesn't ask about the 'Minimum Ridiculous Product' next. That would be a whole other discussion!
upvoted 0 times
Cherry
4 days ago
C) What the MVP is
upvoted 0 times
...
Keneth
6 days ago
B) That the MVP must go into operational use
upvoted 0 times
...
Denna
9 days ago
A) When the MVP will be defined
upvoted 0 times
...
...
Yun
28 days ago
If the MVP isn't going into operational use, what's the point? B is the way to go.
upvoted 0 times
...
Salome
29 days ago
I'm torn between A and C, but I think C is the more comprehensive answer.
upvoted 0 times
...
Madelyn
1 months ago
B seems like the right choice. The MVP has to go into operational use to prove its worth.
upvoted 0 times
Lavonna
19 days ago
I agree, the MVP must go into operational use to show its value.
upvoted 0 times
...
...
Leigha
2 months ago
Definitely not D - the MVP is not the same as project viability. That's just silly.
upvoted 0 times
Mollie
24 days ago
B) That the MVP must go into operational use
upvoted 0 times
...
Brynn
24 days ago
C) What the MVP is
upvoted 0 times
...
Merlyn
1 months ago
A) When the MVP will be defined
upvoted 0 times
...
...
Goldie
2 months ago
The business case should clearly state what the MVP is, so I'm going with option C.
upvoted 0 times
Micheal
28 days ago
I agree, it's important for everyone to be on the same page about that.
upvoted 0 times
...
Joni
1 months ago
I think the business case should definitely state what the MVP is.
upvoted 0 times
...
...
Geoffrey
2 months ago
I agree, the business case should clarify the MVP and its timeline for definition.
upvoted 0 times
...
Floyd
2 months ago
I think it should also mention when the MVP will be defined.
upvoted 0 times
...
Britt
2 months ago
The business case should state what the MVP is.
upvoted 0 times
...

Save Cancel
az-700  pass4success  az-104  200-301  200-201  cissp  350-401  350-201  350-501  350-601  350-801  350-901  az-720  az-305  pl-300  

Warning: Cannot modify header information - headers already sent by (output started at /pass.php:70) in /pass.php on line 77