Actual exam question for PRINCE2's PRINCE2-7-Foundation exam
Question #: 18
Topic #: 1
[All PRINCE2-7-Foundation Questions]

What is the project manager role responsible for?

Show Suggested Answer Hide Answer
Suggested Answer: A

In PRINCE2, baselines are used to establish a reference point for the agreed state of products, against which actual progress can be compared and managed. By requesting a report to check for conflicts between the agreed and actual states of products, the project manager is effectively applying the concept of baselines within issue management. This helps in identifying deviations from the agreed deliverables and initiating corrective actions to address these discrepancies. Reference: (PRINCE2 7 Foundation Handbook, AXELOS)


Contribute your Thoughts:

Annita
6 days ago
B) Ensuring that the project produces the required products seems like the most relevant answer to me. As a project manager, my primary responsibility is to make sure the project delivers what it's supposed to.
upvoted 0 times
...
Romana
19 days ago
I believe the project manager should define the project-level tolerances as well.
upvoted 0 times
...
India
21 days ago
I think the project manager also needs to verify that the project gives value for money.
upvoted 0 times
...
Macy
23 days ago
The project manager role is responsible for ensuring that the project produces the required products.
upvoted 0 times
...

Save Cancel
az-700  pass4success  az-104  200-301  200-201  cissp  350-401  350-201  350-501  350-601  350-801  350-901  az-720  az-305  pl-300  

Warning: Cannot modify header information - headers already sent by (output started at /pass.php:70) in /pass.php on line 77