PMI Exam PMI-RMP Topic 9 Question 73 Discussion

Actual exam question for PMI's PMI-RMP exam
Question #: 73
Topic #: 9
[All PMI-RMP Questions]

A new risk manager has been assigned to a delayed strategic project. The risk manager presented a new plan to get the project back on track using lessons learned and applying risk response strategies. Senior management wants to remove contingency reserves because they want to finish the project earlier.

What should the risk manager do in this scenario?

Show Suggested Answer Hide Answer
Suggested Answer: A

Contribute your Thoughts:

Roy
30 days ago
I'd love to see the risk manager do a risk planning workshop while wearing a superhero cape. That would really get the team excited about tackling the challenges!
upvoted 0 times
...
Tommy
1 months ago
Changing the response strategies might be a good idea, but the risk manager should also review the project schedule to ensure the plan is realistic.
upvoted 0 times
...
Jeannine
1 months ago
A risk planning workshop sounds like the best approach to get the project back on track. The risk manager should work with the team to identify and mitigate the risks.
upvoted 0 times
...
Graciela
1 months ago
Cutting contingency reserves? That's like trying to take the airbags out of a car to make it lighter. Not a good idea!
upvoted 0 times
Alexia
9 days ago
C: Reduce the contingency reserves.
upvoted 0 times
...
Eloisa
17 days ago
B: Conduct a risk planning workshop.
upvoted 0 times
...
Lilli
19 days ago
A: Review project schedule estimates.
upvoted 0 times
...
...
Moon
2 months ago
Reducing the contingency reserves is a risky move. The risk manager should review the project schedule estimates and apply appropriate risk response strategies instead.
upvoted 0 times
Alaine
14 days ago
D) Conduct a risk planning workshop.
upvoted 0 times
...
Art
24 days ago
C) Reduce the contingency reserves.
upvoted 0 times
...
Julian
1 months ago
B) Change the response strategies.
upvoted 0 times
...
Arleen
2 months ago
A) Review project schedule estimates.
upvoted 0 times
...
...
Domitila
2 months ago
Reducing contingency reserves could be risky. It's better to conduct a risk planning workshop.
upvoted 0 times
...
Lili
2 months ago
I agree with Evan. Changing response strategies might not be enough.
upvoted 0 times
...
Evan
2 months ago
I think the risk manager should review project schedule estimates.
upvoted 0 times
...

Save Cancel