When processing freight invoices for a project, the project manager notices the shipping costs exceeded the budget due to increased fuel costs. The risk manager included this risk in the project's contingency allowance. When reviewing the project budget execution reports, the project manager notices unused budget remaining in other closed tasks of the project that could cover the additional shipping costs.
What should the project manager do?
Erick
2 months agoJavier
27 days agoHaydee
1 months agoAide
1 months agoNaomi
1 months agoBrendan
2 months agoDelfina
2 months agoDesmond
2 months agoLeslie
2 months agoBrett
20 days agoPatria
23 days agoRessie
1 months agoAlpha
2 months agoFausto
2 months agoMelita
3 months ago