The risk manager for an IT project developing a software application has a major stakeholder concerned that the project will not conclude within the available funding. The risk manager found delays in the iterations and increments in the project's budget, potentially increasing the duration by two weeks.
What tools should the risk manager use to properly decide the risk of not finishing the project within the budget?
Candida
1 months agoJacquelyne
2 months agoGerman
1 days agoJavier
3 days agoAlton
3 days agoDestiny
4 days agoShoshana
4 days agoChun
6 days agoLauran
1 months agoYan
1 months agoBeth
2 months agoAleta
1 months agoDerick
1 months agoTien
2 months agoAnnamaria
13 days agoCary
14 days agoLucia
15 days agoJaleesa
1 months agoAlita
2 months agoMarci
2 months agoJenise
3 months agoBong
3 months ago