Deal of The Day! Hurry Up, Grab the Special Discount - Save 25% - Ends In 00:00:00 Coupon code: SAVE25
Welcome to Pass4Success

- Free Preparation Discussions

PMI Exam PMI-RMP Topic 7 Question 85 Discussion

Actual exam question for PMI's PMI-RMP exam
Question #: 85
Topic #: 7
[All PMI-RMP Questions]

A risk manager recently had to take an unexpected leave of absence. An interim risk manager has been tasked with completing risk planning for a new project. The interim risk manager has been provided with a strength, weaknesses, opportunities, and threats (SWOT) analysis that was completed during a project kickoff meeting several weeks ago.

What should the interim risk manager do to derive actionable risk responses from the SWOT analysis?

Show Suggested Answer Hide Answer
Suggested Answer: A

Contribute your Thoughts:

Melynda
15 days ago
The SWOT analysis is a great starting point, but the interim manager needs to dig deeper to derive actionable risk responses. I think option B is the way to go - collaborating with the project sponsor to prioritize the SWOT items is key.
upvoted 0 times
...
Hubert
17 days ago
I believe working with the project sponsor to understand their priorities (Option B) is also crucial in this situation.
upvoted 0 times
...
Ivette
22 days ago
I agree with Matilda. It's important to prioritize and categorize the risks to develop effective responses.
upvoted 0 times
...
Matilda
24 days ago
I think the interim risk manager should determine risks from the SWOT analysis and break them down into threats and opportunities (Option A).
upvoted 0 times
...

Save Cancel
az-700  pass4success  az-104  200-301  200-201  cissp  350-401  350-201  350-501  350-601  350-801  350-901  az-720  az-305  pl-300  

Warning: Cannot modify header information - headers already sent by (output started at /pass.php:70) in /pass.php on line 77