Independence Day Deal! Unlock 25% OFF Today – Limited-Time Offer - Ends In 00:00:00 Coupon code: SAVE25
Welcome to Pass4Success

- Free Preparation Discussions

PMI Exam PMI-RMP Topic 5 Question 64 Discussion

Actual exam question for PMI's PMI-RMP exam
Question #: 64
Topic #: 5
[All PMI-RMP Questions]

A risk manager has to Inform a project sponsor of the expected duration of an entire project. The project has three main tasks, each with different probabilities of duration. Which analytical tool should the risk manager use?

Show Suggested Answer Hide Answer
Suggested Answer: A

Contribute your Thoughts:

Xenia
1 months ago
I bet the risk manager is just hoping the project sponsor doesn't ask too many questions. Monte Carlo is the way to go, though!
upvoted 0 times
...
Karl
1 months ago
Probability tree diagram? Sounds like someone's been reading too many textbooks. Monte Carlo is the practical choice for this scenario.
upvoted 0 times
Bette
14 days ago
I've used Monte Carlo simulation before, it's really effective for analyzing project durations.
upvoted 0 times
...
Rosenda
25 days ago
I agree, it's the most practical tool to use in this situation.
upvoted 0 times
...
Romana
29 days ago
Monte Carlo simulation is definitely the way to go for this project.
upvoted 0 times
...
...
Rebeca
2 months ago
Haha, an Ishikawa diagram? That's for cause-and-effect analysis, not project risk management. Seems like someone's trying to throw us off the trail!
upvoted 0 times
Franchesca
5 days ago
A: Definitely, it's a more appropriate tool for project risk management than an Ishikawa diagram.
upvoted 0 times
...
Virgie
12 days ago
B: Yeah, that makes sense. It can help account for the different probabilities of duration for each task.
upvoted 0 times
...
Shenika
1 months ago
A: I think the risk manager should use Monte Carlo simulation.
upvoted 0 times
...
...
Jina
2 months ago
Decision tree analysis could work too, but that's more for branching outcomes, not estimating project duration.
upvoted 0 times
Vanesa
1 days ago
A: I think the risk manager should use Monte Carlo simulation.
upvoted 0 times
...
Meghann
5 days ago
D: Yeah, I think Monte Carlo simulation takes into account the different probabilities of duration for each task in the project.
upvoted 0 times
...
Andra
8 days ago
C: Decision tree analysis could work too, but it's more for branching outcomes, not estimating project duration.
upvoted 0 times
...
Gennie
15 days ago
B: I agree, Monte Carlo simulation would be the best analytical tool for estimating project duration.
upvoted 0 times
...
Kristeen
1 months ago
A: I think the risk manager should use Monte Carlo simulation.
upvoted 0 times
...
...
Cristy
2 months ago
Monte Carlo simulation is definitely the way to go here. It's the only tool that can handle the different probabilities and durations of the project tasks.
upvoted 0 times
...
Francis
2 months ago
I'm not sure. Decision tree analysis could also be useful in this situation to map out different decision paths.
upvoted 0 times
...
Annmarie
2 months ago
I agree with Jordan. Monte Carlo simulation can provide a range of possible outcomes based on different probabilities.
upvoted 0 times
...
Jordan
3 months ago
I think the risk manager should use Monte Carlo simulation.
upvoted 0 times
...

Save Cancel
az-700  pass4success  az-104  200-301  200-201  cissp  350-401  350-201  350-501  350-601  350-801  350-901  az-720  az-305  pl-300  

Warning: Cannot modify header information - headers already sent by (output started at /pass.php:70) in /pass.php on line 77