Deal of The Day! Hurry Up, Grab the Special Discount - Save 25% - Ends In 00:00:00 Coupon code: SAVE25
Welcome to Pass4Success

- Free Preparation Discussions

PMI Exam PMI-RMP Topic 5 Question 64 Discussion

Actual exam question for PMI's PMI-RMP exam
Question #: 64
Topic #: 5
[All PMI-RMP Questions]

A risk manager has to Inform a project sponsor of the expected duration of an entire project. The project has three main tasks, each with different probabilities of duration. Which analytical tool should the risk manager use?

Show Suggested Answer Hide Answer
Suggested Answer: A

Contribute your Thoughts:

Jina
5 days ago
Decision tree analysis could work too, but that's more for branching outcomes, not estimating project duration.
upvoted 0 times
...
Cristy
8 days ago
Monte Carlo simulation is definitely the way to go here. It's the only tool that can handle the different probabilities and durations of the project tasks.
upvoted 0 times
...
Francis
12 days ago
I'm not sure. Decision tree analysis could also be useful in this situation to map out different decision paths.
upvoted 0 times
...
Annmarie
14 days ago
I agree with Jordan. Monte Carlo simulation can provide a range of possible outcomes based on different probabilities.
upvoted 0 times
...
Jordan
25 days ago
I think the risk manager should use Monte Carlo simulation.
upvoted 0 times
...

Save Cancel
az-700  pass4success  az-104  200-301  200-201  cissp  350-401  350-201  350-501  350-601  350-801  350-901  az-720  az-305  pl-300  

Warning: Cannot modify header information - headers already sent by (output started at /pass.php:70) in /pass.php on line 77