A risk manager has to Inform a project sponsor of the expected duration of an entire project. The project has three main tasks, each with different probabilities of duration. Which analytical tool should the risk manager use?
Monte Carlo simulation is definitely the way to go here. It's the only tool that can handle the different probabilities and durations of the project tasks.
Xenia
1 months agoKarl
1 months agoBette
14 days agoRosenda
25 days agoRomana
29 days agoRebeca
2 months agoFranchesca
5 days agoVirgie
12 days agoShenika
1 months agoJina
2 months agoVanesa
1 days agoMeghann
5 days agoAndra
8 days agoGennie
15 days agoKristeen
1 months agoCristy
2 months agoFrancis
2 months agoAnnmarie
2 months agoJordan
3 months ago