A project manager managing a high-risk rating project was just informed that one of the key project resources has decided to leave the organization. The project manager asks the risk manager for their recommendations. The risk manager previously identified this as a risk and had created a transition plan to enable another resource to carry out the same duties The risk manager was informed that by transitioning the responsibilities to the new resource, new risks to the completion dates of other project-related tasks appear.
What should the risk manager advise the project manager?
Ruthann
29 days agoMona
7 days agoMonte
1 months agoPaulina
7 days agoAlfred
17 days agoEllsworth
1 months agoVal
1 days agoAntonio
3 days agoCarylon
9 days agoJaime
2 months agoPatti
15 days agoBilly
16 days agoErnest
23 days agoAshleigh
2 months agoBritt
4 days agoWillis
17 days agoNenita
1 months agoCarin
1 months agoReiko
2 months agoRusty
2 months agoWendell
2 months agoKallie
2 months ago