Independence Day Deal! Unlock 25% OFF Today – Limited-Time Offer - Ends In 00:00:00 Coupon code: SAVE25
Welcome to Pass4Success

- Free Preparation Discussions

PMI Exam PMI-RMP Topic 4 Question 91 Discussion

Actual exam question for PMI's PMI-RMP exam
Question #: 91
Topic #: 4
[All PMI-RMP Questions]

A project manager managing a high-risk rating project was just informed that one of the key project resources has decided to leave the organization. The project manager asks the risk manager for their recommendations. The risk manager previously identified this as a risk and had created a transition plan to enable another resource to carry out the same duties The risk manager was informed that by transitioning the responsibilities to the new resource, new risks to the completion dates of other project-related tasks appear.

What should the risk manager advise the project manager?

Show Suggested Answer Hide Answer
Suggested Answer: A

Contribute your Thoughts:

Ruthann
29 days ago
I bet the risk manager is wishing they had a risk management plan that could handle the unexpected. Maybe they should have consulted a magic 8-ball instead.
upvoted 0 times
Mona
7 days ago
The risk manager should advise the project manager to review the transition plan and assess the impact of the new risks.
upvoted 0 times
...
...
Monte
1 months ago
A is a cop-out. You can't just accept new risks without a proper plan. The risk manager needs to be proactive and address these issues.
upvoted 0 times
Paulina
7 days ago
We should update the risk register and develop mitigation strategies for the new risks that have emerged.
upvoted 0 times
...
Alfred
17 days ago
We need to reassess the impact of transitioning the responsibilities to the new resource.
upvoted 0 times
...
...
Ellsworth
1 months ago
D is the way to go. Escalating the new risks to the stakeholders is crucial to ensure proper communication and buy-in for the risk management process.
upvoted 0 times
Val
1 days ago
D) Escalate the new risks immediately to the project stakeholders to ensure proper risk communication is in place.
upvoted 0 times
...
Antonio
3 days ago
B) Address these secondary risks as per the risk management plan
upvoted 0 times
...
Carylon
9 days ago
A) Apply a risk acceptance strategy to the new risks as there is no risk response plan.
upvoted 0 times
...
...
Jaime
2 months ago
I think C is the best option. The risk manager should update the plan to reflect the new probabilities and impacts, and then adjust the response accordingly.
upvoted 0 times
Patti
15 days ago
C) Update the risk management plan with the new probability/impact and change the response.
upvoted 0 times
...
Billy
16 days ago
B) Address these secondary risks as per the risk management plan
upvoted 0 times
...
Ernest
23 days ago
A) Apply a risk acceptance strategy to the new risks as there is no risk response plan.
upvoted 0 times
...
...
Ashleigh
2 months ago
Option B seems like the most logical choice. The risk management plan should already have provisions for addressing any secondary risks that arise from the initial risk response.
upvoted 0 times
Britt
4 days ago
D) Escalate the new risks immediately to the project stakeholders to ensure proper risk communication is in place.
upvoted 0 times
...
Willis
17 days ago
C) Update the risk management plan with the new probability/impact and change the response.
upvoted 0 times
...
Nenita
1 months ago
C) Update the risk management plan with the new probability/impact and change the response.
upvoted 0 times
...
Carin
1 months ago
B) Address these secondary risks as per the risk management plan
upvoted 0 times
...
Reiko
2 months ago
B) Address these secondary risks as per the risk management plan
upvoted 0 times
...
...
Rusty
2 months ago
I believe the risk manager should also update the risk management plan with the new probability/impact and change the response accordingly.
upvoted 0 times
...
Wendell
2 months ago
I agree with Kallie. It's important to follow the risk management plan to mitigate any potential negative impacts on the project.
upvoted 0 times
...
Kallie
2 months ago
I think the risk manager should advise the project manager to address these secondary risks as per the risk management plan.
upvoted 0 times
...

Save Cancel
az-700  pass4success  az-104  200-301  200-201  cissp  350-401  350-201  350-501  350-601  350-801  350-901  az-720  az-305  pl-300  

Warning: Cannot modify header information - headers already sent by (output started at /pass.php:70) in /pass.php on line 77