PMI Exam PMI-RMP Topic 4 Question 66 Discussion

Actual exam question for PMI's PMI-RMP exam
Question #: 66
Topic #: 4
[All PMI-RMP Questions]

During project execution tor a software development program a risk manager notices the results vary from the stated expectations in the planning phase. The project team states that there was unrealistic planning.

What should the risk manager do next to understand the differences between planning and execution?

Show Suggested Answer Hide Answer
Suggested Answer: A

Contribute your Thoughts:

Shakira
1 months ago
I bet the project team is just making excuses because they spent the entire budget on a fancy team-building retreat at a luxury resort. The risk manager should probably just follow the money trail.
upvoted 0 times
...
Rosendo
1 months ago
Engaging with the team is the way to go. They're the ones who can provide the insights on what went wrong. Plus, it's always fun to see them squirm when the risk manager starts asking tough questions.
upvoted 0 times
Lasandra
10 days ago
It's important to gather feedback from the team to understand their perspective on the discrepancies.
upvoted 0 times
...
Sherell
14 days ago
We should conduct a root cause analysis to identify where the planning went wrong.
upvoted 0 times
...
Ricarda
15 days ago
Let's review the initial project plan and compare it to what actually happened.
upvoted 0 times
...
...
Tracie
2 months ago
Prepare a management of change (MOC) to adjust the project cost and duration? That's like trying to put a bandaid on a broken leg. We need to dig deeper and find the real problem!
upvoted 0 times
Stanton
15 days ago
C) Engage with the team to present the actual results to the sponsor.
upvoted 0 times
...
Carmen
18 days ago
B) Review the assumptions to understand any change.
upvoted 0 times
...
Wilda
1 months ago
A) Move forward with the lessons learned from the sprint.
upvoted 0 times
...
...
Dorothy
2 months ago
Presenting the actual results to the sponsor is a great idea. They need to be informed of the discrepancies between planning and execution.
upvoted 0 times
...
Skye
2 months ago
The risk manager should definitely review the assumptions to understand any changes that occurred. Lessons learned from the sprint are good, but getting to the root of the issue is crucial.
upvoted 0 times
Lamonica
29 days ago
D) Engage with the team to present the actual results to the sponsor.
upvoted 0 times
...
Shawna
1 months ago
B) Review the assumptions to understand any change.
upvoted 0 times
...
Phyliss
1 months ago
D) Engage with the team to present the actual results to the sponsor.
upvoted 0 times
...
Justine
1 months ago
B) Review the assumptions to understand any change.
upvoted 0 times
...
...
Melvin
2 months ago
I think preparing a management of change (MOC) to adjust the project cost and duration could also be helpful in this situation.
upvoted 0 times
...
Valda
2 months ago
I agree with Malcom. It's important to identify where the planning went wrong.
upvoted 0 times
...
Malcom
2 months ago
I think the risk manager should review the assumptions to understand any change.
upvoted 0 times
...

Save Cancel
az-700  pass4success  az-104  200-301  200-201  cissp  350-401  350-201  350-501  350-601  350-801  350-901  az-720  az-305  pl-300  

Warning: Cannot modify header information - headers already sent by (output started at /pass.php:70) in /pass.php on line 77