PMI Exam PMI-RMP Topic 4 Question 66 Discussion

Actual exam question for PMI's PMI-RMP exam
Question #: 66
Topic #: 4
[All PMI-RMP Questions]

During project execution tor a software development program a risk manager notices the results vary from the stated expectations in the planning phase. The project team states that there was unrealistic planning.

What should the risk manager do next to understand the differences between planning and execution?

Show Suggested Answer Hide Answer
Suggested Answer: A

Contribute your Thoughts:

Tracie
2 days ago
Prepare a management of change (MOC) to adjust the project cost and duration? That's like trying to put a bandaid on a broken leg. We need to dig deeper and find the real problem!
upvoted 0 times
...
Dorothy
6 days ago
Presenting the actual results to the sponsor is a great idea. They need to be informed of the discrepancies between planning and execution.
upvoted 0 times
...
Skye
9 days ago
The risk manager should definitely review the assumptions to understand any changes that occurred. Lessons learned from the sprint are good, but getting to the root of the issue is crucial.
upvoted 0 times
...
Melvin
15 days ago
I think preparing a management of change (MOC) to adjust the project cost and duration could also be helpful in this situation.
upvoted 0 times
...
Valda
15 days ago
I agree with Malcom. It's important to identify where the planning went wrong.
upvoted 0 times
...
Malcom
21 days ago
I think the risk manager should review the assumptions to understand any change.
upvoted 0 times
...

Save Cancel