Deal of The Day! Hurry Up, Grab the Special Discount - Save 25% - Ends In 00:00:00 Coupon code: SAVE25
Welcome to Pass4Success

- Free Preparation Discussions

PMI Exam PMI-RMP Topic 2 Question 77 Discussion

Actual exam question for PMI's PMI-RMP exam
Question #: 77
Topic #: 2
[All PMI-RMP Questions]

A budget change request was initiated by a functional manager in an organization due to a shortage in the functional manager's department budget. The functional manager asks the CEO to approve utilization of a contingency budget reserved for one of the projects in its closing phase.

What should the risk manager of the related project have done to prevent this situation from happening?

Show Suggested Answer Hide Answer
Suggested Answer: A, B, D

Contribute your Thoughts:

Lashandra
6 hours ago
Creating the project work plan and budget more accurately seems like the best option here. If the budget was planned properly, there wouldn't have been a shortage in the first place.
upvoted 0 times
...
Dominga
12 days ago
Maybe educating the project team on budget change requests could have also helped in this situation.
upvoted 0 times
...
Wenona
14 days ago
I think the risk manager should have reformed the risk monitoring and closing process properly. Having a robust process in place could have helped prevent this situation.
upvoted 0 times
...
Marg
17 days ago
I agree with Colby, better risk management could have prevented this budget shortage.
upvoted 0 times
...
Colby
19 days ago
The risk manager should have reformed the risk monitoring and closing process properly.
upvoted 0 times
...

Save Cancel
az-700  pass4success  az-104  200-301  200-201  cissp  350-401  350-201  350-501  350-601  350-801  350-901  az-720  az-305  pl-300  

Warning: Cannot modify header information - headers already sent by (output started at /pass.php:70) in /pass.php on line 77