Independence Day Deal! Unlock 25% OFF Today – Limited-Time Offer - Ends In 00:00:00 Coupon code: SAVE25
Welcome to Pass4Success

- Free Preparation Discussions

PMI Exam PMI-RMP Topic 2 Question 77 Discussion

Actual exam question for PMI's PMI-RMP exam
Question #: 77
Topic #: 2
[All PMI-RMP Questions]

A budget change request was initiated by a functional manager in an organization due to a shortage in the functional manager's department budget. The functional manager asks the CEO to approve utilization of a contingency budget reserved for one of the projects in its closing phase.

What should the risk manager of the related project have done to prevent this situation from happening?

Show Suggested Answer Hide Answer
Suggested Answer: A, B, D

Contribute your Thoughts:

Rosio
1 months ago
I bet the risk manager was too busy playing Tetris to properly monitor the project's budget. That's the real reason this situation happened.
upvoted 0 times
...
Ammie
1 months ago
Haha, the risk manager should have consulted a crystal ball to predict the future budget needs. That would have been more effective than any of these options!
upvoted 0 times
...
Mattie
1 months ago
Communicating better with the CEO? Really? I doubt that would have made a difference. The risk manager should have been on top of the project's finances and not let it get to this point.
upvoted 0 times
Marion
15 days ago
C: Educating the project team on budget change requests could have also been beneficial in preventing this shortage.
upvoted 0 times
...
Judy
23 days ago
B: Yeah, creating a more accurate project work plan and budget would have helped avoid this situation.
upvoted 0 times
...
Sylvie
29 days ago
A: The risk manager should have reformed the risk monitoring and closing process properly.
upvoted 0 times
...
...
Silvana
1 months ago
Educating the project team on budget change requests is a good idea, but I don't think it would have solved the root cause of the problem. The risk manager needs to be proactive in managing the project's budget.
upvoted 0 times
...
Lashandra
2 months ago
Creating the project work plan and budget more accurately seems like the best option here. If the budget was planned properly, there wouldn't have been a shortage in the first place.
upvoted 0 times
Pearly
14 days ago
User 3: Reformed risk monitoring and closing process could have also helped in avoiding this situation.
upvoted 0 times
...
Yen
23 days ago
User 2: That's true, proper planning could have prevented the budget shortage.
upvoted 0 times
...
Linsey
1 months ago
User 1: The risk manager should have created the project work plan and budget more accurately.
upvoted 0 times
...
...
Dominga
2 months ago
Maybe educating the project team on budget change requests could have also helped in this situation.
upvoted 0 times
...
Wenona
2 months ago
I think the risk manager should have reformed the risk monitoring and closing process properly. Having a robust process in place could have helped prevent this situation.
upvoted 0 times
Albina
27 days ago
B) Created the project work plan and budget more accurately.
upvoted 0 times
...
Nobuko
29 days ago
A) Reformed the risk monitoring and closing process properly.
upvoted 0 times
...
...
Marg
2 months ago
I agree with Colby, better risk management could have prevented this budget shortage.
upvoted 0 times
...
Colby
2 months ago
The risk manager should have reformed the risk monitoring and closing process properly.
upvoted 0 times
...

Save Cancel
az-700  pass4success  az-104  200-301  200-201  cissp  350-401  350-201  350-501  350-601  350-801  350-901  az-720  az-305  pl-300  

Warning: Cannot modify header information - headers already sent by (output started at /pass.php:70) in /pass.php on line 77