Independence Day Deal! Unlock 25% OFF Today – Limited-Time Offer - Ends In 00:00:00 Coupon code: SAVE25
Welcome to Pass4Success

- Free Preparation Discussions

PMI Exam PMI-RMP Topic 10 Question 69 Discussion

Actual exam question for PMI's PMI-RMP exam
Question #: 69
Topic #: 10
[All PMI-RMP Questions]

A project baseline included a budget of USS900 million and a 12-month schedule. Three months into the project a risk manager collected performance data on the project expenditure showing an actual cumulative lost.

What should the risk manager use to ascertain the cost performance risk?

Show Suggested Answer Hide Answer
Suggested Answer: A

Contribute your Thoughts:

Yuette
30 days ago
Sentiment analysis? That's like using a crystal ball to predict the weather. Variance analysis is the way to go, folks. It's the Swiss Army knife of project management tools.
upvoted 0 times
Bong
2 days ago
I agree, it's like having a magic wand to see where things are going off track.
upvoted 0 times
...
Jonell
5 days ago
Variance analysis is definitely the way to go. It gives a clear picture of cost performance.
upvoted 0 times
...
...
Derick
1 months ago
Cluster analysis? What is this, a high school science fair project? Variance analysis is the only way to get a clear picture of the cost performance risk. Anything else is just a distraction.
upvoted 0 times
...
Maybelle
2 months ago
I'm not sure, but I think PESTLE analysis could also be useful in assessing the cost performance risk.
upvoted 0 times
...
Dierdre
2 months ago
I agree with Tarra, variance analysis would provide insights into the project's cost performance.
upvoted 0 times
...
Verona
2 months ago
PESTLE analysis? Really? That's like trying to fix a leaky faucet with a sledgehammer. Variance analysis is the way to go, no doubt about it.
upvoted 0 times
Von
24 days ago
Variance analysis is the way to go, no doubt about it.
upvoted 0 times
...
Jessenia
25 days ago
PESTLE analysis? Really? That's like trying to fix a leaky faucet with a sledgehammer.
upvoted 0 times
...
Ronnie
27 days ago
Variance analysis is the way to go, no doubt about it.
upvoted 0 times
...
Polly
1 months ago
PESTLE analysis? Really? That's like trying to fix a leaky faucet with a sledgehammer.
upvoted 0 times
...
...
Tarra
2 months ago
I think the risk manager should use variance analysis to ascertain the cost performance risk.
upvoted 0 times
...
France
2 months ago
I'm not sure, but I think PESTLE analysis could also be useful in understanding the external factors affecting cost performance.
upvoted 0 times
...
Jerrod
2 months ago
Ah, variance analysis - the trusty tool to uncover the cost performance risk. Gotta love how it cuts through the data like a hot knife through butter!
upvoted 0 times
...
Ciara
2 months ago
I agree with Novella, variance analysis would be the best option to analyze the cost performance risk.
upvoted 0 times
...
Novella
2 months ago
I think the risk manager should use variance analysis to ascertain the cost performance risk.
upvoted 0 times
...

Save Cancel
az-700  pass4success  az-104  200-301  200-201  cissp  350-401  350-201  350-501  350-601  350-801  350-901  az-720  az-305  pl-300  

Warning: Cannot modify header information - headers already sent by (output started at /pass.php:70) in /pass.php on line 77