A project baseline included a budget of USS900 million and a 12-month schedule. Three months into the project a risk manager collected performance data on the project expenditure showing an actual cumulative lost.
What should the risk manager use to ascertain the cost performance risk?
Yuette
30 days agoBong
2 days agoJonell
5 days agoDerick
1 months agoMaybelle
2 months agoDierdre
2 months agoVerona
2 months agoVon
24 days agoJessenia
25 days agoRonnie
27 days agoPolly
1 months agoTarra
2 months agoFrance
2 months agoJerrod
2 months agoCiara
2 months agoNovella
2 months ago