A project baseline included a budget of USS900 million and a 12-month schedule. Three months into the project a risk manager collected performance data on the project expenditure showing an actual cumulative lost.
What should the risk manager use to ascertain the cost performance risk?
Maybelle
7 days agoDierdre
9 days agoVerona
11 days agoTarra
13 days agoFrance
14 days agoJerrod
15 days agoCiara
17 days agoNovella
20 days ago