PMI Exam PMI-PBA Topic 7 Question 85 Discussion

Actual exam question for PMI's PMI-PBA exam
Question #: 85
Topic #: 7
[All PMI-PBA Questions]

In the middle of a project, a new requirement was added to the scope. The business analyst must determine if any impacts, dependencies, or risks are associated with the addition to the scope.

What task should the business analyst perform in order to identify these impacts?

Show Suggested Answer Hide Answer
Suggested Answer: A

Contribute your Thoughts:

Hollis
1 months ago
Hold up, what if the new requirement is to install a trampoline in the office? Wouldn't that impact, like, the whole building's structural integrity? Just sayin'.
upvoted 0 times
Gerald
2 days ago
B) Manage requirements traceability.
upvoted 0 times
...
Leah
16 days ago
A) Manage solution scope.
upvoted 0 times
...
...
Kati
1 months ago
I'm voting for B too. Gotta love those traceability matrices, they're like a treasure map for project managers. Plus, it's the only answer that doesn't sound like a boring bureaucratic task.
upvoted 0 times
...
Leonora
2 months ago
C is tempting, but prioritizing requirements doesn't address the need to identify specific impacts. I'll go with B - traceability all the way!
upvoted 0 times
King
5 days ago
I think managing assumptions and constraints is crucial to consider when identifying impacts.
upvoted 0 times
...
Blythe
9 days ago
C) Manage requirements prioritization.
upvoted 0 times
...
Lai
9 days ago
Managing solution scope is also important to ensure the project stays on track.
upvoted 0 times
...
Adrianna
13 days ago
I agree, traceability is key to understanding the impacts of new requirements.
upvoted 0 times
...
Jean
14 days ago
B) Manage requirements traceability.
upvoted 0 times
...
Jame
1 months ago
A) Manage solution scope.
upvoted 0 times
...
...
Benton
2 months ago
I'm torn between B and D. While traceability is important, managing assumptions and constraints could also reveal those hidden impacts. Hmm, tough call.
upvoted 0 times
...
Florinda
2 months ago
Definitely B. Manage requirements traceability. That's the key to understanding how new requirements impact the existing project scope and deliverables.
upvoted 0 times
...
Dalene
2 months ago
I believe managing assumptions and constraints is also important to consider potential risks.
upvoted 0 times
...
Cherry
2 months ago
I agree with Edna. Managing solution scope will help identify impacts and dependencies.
upvoted 0 times
...
Edna
2 months ago
I think the business analyst should manage solution scope.
upvoted 0 times
...

Save Cancel