Independence Day Deal! Unlock 25% OFF Today – Limited-Time Offer - Ends In 00:00:00 Coupon code: SAVE25
Welcome to Pass4Success

- Free Preparation Discussions

PMI Exam PMI-ACP Topic 5 Question 96 Discussion

Actual exam question for PMI's PMI-ACP exam
Question #: 96
Topic #: 5
[All PMI-ACP Questions]

A company is considering developing a new, complex application that will require a large initial investment. However, if successful, the profit potential is high. When preparing an analysis, what should be used to encourage stakeholders who are concerned about project failure to authorize the initial investment?

Show Suggested Answer Hide Answer
Suggested Answer: C

Contribute your Thoughts:

Suzi
1 months ago
All these options sound pretty technical. I'm just hoping the exam doesn't ask me to do any complex math. That would be a real nightmare!
upvoted 0 times
...
Cletus
1 months ago
C) Story points rather than cost estimates? That's an interesting idea, but I'm not sure it would be enough to sway stakeholders who are worried about the initial investment.
upvoted 0 times
Laquanda
11 days ago
D) Calculated earned value (EV)
upvoted 0 times
...
Elroy
12 days ago
C) Story points rather than cost estimates
upvoted 0 times
...
Lashandra
13 days ago
B) Many small minimally marketable features (MMFs)
upvoted 0 times
...
Mozell
1 months ago
A) Calculated planned percent complete (PPC)
upvoted 0 times
...
...
Myrtie
2 months ago
A) Calculated planned percent complete (PPC)? Sounds like something a project manager would use, but probably not the best way to get stakeholders on board.
upvoted 0 times
Brandee
8 days ago
D) Calculated earned value (EV)
upvoted 0 times
...
Lynelle
28 days ago
C) Story points rather than cost estimates
upvoted 0 times
...
Hillary
1 months ago
B) Many small minimally marketable features (MMFs)
upvoted 0 times
...
Norah
1 months ago
C) Story points rather than cost estimates
upvoted 0 times
...
Sanda
1 months ago
B) Many small minimally marketable features (MMFs)
upvoted 0 times
...
...
Marti
2 months ago
I'm not sure D) Calculated earned value (EV) is the right choice. That's more for tracking project performance, not convincing stakeholders to invest.
upvoted 0 times
...
Jade
2 months ago
B) Many small minimally marketable features (MMFs) seems like the best option here. It's a great way to demonstrate progress and reduce the risk of failure.
upvoted 0 times
Bernadine
23 days ago
D: Calculated earned value (EV) might be more convincing for stakeholders concerned about project failure.
upvoted 0 times
...
Virgilio
27 days ago
C: Story points rather than cost estimates could also be useful in gaining stakeholder buy-in.
upvoted 0 times
...
Viva
1 months ago
B: Agreed, it can help reduce the risk of failure and keep stakeholders engaged.
upvoted 0 times
...
Andree
2 months ago
A: I think using Many small minimally marketable features (MMFs) is a good idea to show progress.
upvoted 0 times
...
...
Detra
2 months ago
I'm not sure about using calculated earned value (EV). Maybe we should consider using story points rather than cost estimates to show the project's progress.
upvoted 0 times
...
Tijuana
2 months ago
I agree with Nicholle. Calculated earned value (EV) will help stakeholders see the financial benefits of the project.
upvoted 0 times
...
Nicholle
3 months ago
I think we should use calculated earned value (EV) to show stakeholders the potential return on investment.
upvoted 0 times
...

Save Cancel
az-700  pass4success  az-104  200-301  200-201  cissp  350-401  350-201  350-501  350-601  350-801  350-901  az-720  az-305  pl-300  

Warning: Cannot modify header information - headers already sent by (output started at /pass.php:70) in /pass.php on line 77