PMI Exam PMI-ACP Topic 1 Question 95 Discussion

Actual exam question for PMI's PMI-ACP exam
Question #: 95
Topic #: 1
[All PMI-ACP Questions]

A learn member 15 stressed due to a heavy workload, while other team members have some slack in their schedules How should the learn lead address this?

Show Suggested Answer Hide Answer
Suggested Answer: C

Contribute your Thoughts:

Augustine
1 months ago
I'm torn between B and C, but I think C is the winner. A little one-on-one time to brainstorm solutions is exactly what the stressed team member needs. Teamwork makes the dream work!
upvoted 0 times
Anika
12 days ago
Let's schedule a meeting to discuss how we can help you with your workload.
upvoted 0 times
...
...
Sean
1 months ago
Option A makes sense, but I feel like the team lead should try to solve this within the team first before escalating to management. Give the team member some support before bringing in the big guns.
upvoted 0 times
Kristian
8 days ago
A: Let's discuss this in our daily stand up meetings.
upvoted 0 times
...
...
Denae
1 months ago
Haha, option D sounds like a recipe for disaster! Tracking tasks like that is just going to add more stress and bureaucracy. Let's keep it simple and human.
upvoted 0 times
...
Lorita
2 months ago
I'd go with option B. Discussing the issue in the daily stand-up meetings allows the whole team to be aware and potentially offer suggestions. Transparency is key.
upvoted 0 times
Micaela
7 days ago
C: Agreed, transparency is important in situations like this. Let's bring it up in the next meeting.
upvoted 0 times
...
Lavonna
11 days ago
B: That sounds like a good idea. It will help keep everyone informed and maybe we can come up with some solutions together.
upvoted 0 times
...
Callie
1 months ago
A: I think we should go with option B and discuss it in our daily stand-up meetings.
upvoted 0 times
...
...
Lashawn
2 months ago
Option C is the way to go! Addressing the issue directly with the stressed team member and brainstorming solutions is the most effective approach. The team lead needs to be proactive and supportive.
upvoted 0 times
Florinda
28 days ago
B) Discuss the issue with the team in daily stand up meetings
upvoted 0 times
...
Royal
1 months ago
A) inform management, and suggest that additional resources may be required
upvoted 0 times
...
Lino
1 months ago
C) Meet personally with the stressed learn member to brainstorm ways to better manage their time
upvoted 0 times
...
...
Eleni
2 months ago
I think informing management and suggesting additional resources may be required could also be helpful in this situation.
upvoted 0 times
...
Melynda
2 months ago
I agree with Julio. It's important to address the issue directly and find solutions together.
upvoted 0 times
...
Julio
3 months ago
I think the learn lead should meet personally with the stressed learn member to brainstorm ways to better manage their time.
upvoted 0 times
...

Save Cancel
az-700  pass4success  az-104  200-301  200-201  cissp  350-401  350-201  350-501  350-601  350-801  350-901  az-720  az-305  pl-300  

Warning: Cannot modify header information - headers already sent by (output started at /pass.php:70) in /pass.php on line 77