PMI Exam PMI-200 Topic 6 Question 58 Discussion

Actual exam question for PMI's PMI-200 exam
Question #: 58
Topic #: 6
[All PMI-200 Questions]

A ScrumMaster consistently holds Daily Scrums and keeps them to 15 minutes or less. The ScrumMaster brings a list of assigned tasks and checks the status of each task with the relevant team members. The ScrumMaster then assigns new tasks for the day and ends the meeting. Is this an appropriate approach to running Daily Scrums?

Show Suggested Answer Hide Answer
Suggested Answer: D

Contribute your Thoughts:

Eulah
1 years ago
True. And C sounds negative. Retrospectives should be positive.
upvoted 0 times
...
Raelene
1 years ago
Good point. B feels off. It's more about the team, not sponsors.
upvoted 0 times
...
Dominga
1 years ago
Increasing empowerment and enjoyment boosts team morale.
upvoted 0 times
...
Erick
1 years ago
Really? Why A?
upvoted 0 times
...
Dominga
1 years ago
It's interesting. I think the right answer is A.
upvoted 0 times
...
Eulah
1 years ago
What do you think about the question in the exam?
upvoted 0 times
...