PMI Exam PMI-100 Topic 3 Question 71 Discussion

Actual exam question for PMI's PMI-100 exam
Question #: 71
Topic #: 3
[All PMI-100 Questions]

What risk technique is used to quantify the probability and impact of risks on project objectives?

Show Suggested Answer Hide Answer
Suggested Answer: C

Contribute your Thoughts:

Kimberely
1 years ago
Yeah, C is definitely about using the matrix to analyze risk qualitatively.
upvoted 0 times
...
Ivory
1 years ago
True, but B is more about planning, not the matrix specifically.
upvoted 0 times
...
Emily
1 years ago
But what about B? Developing a risk register is important too.
upvoted 0 times
...
Staci
1 years ago
Agreed, C seems right. Perform Qualitative Risk Analysis fits well.
upvoted 0 times
...
Kimberely
1 years ago
I think it's C. It evaluates each risk's importance and priority.
upvoted 0 times
...
Ivory
1 years ago
What do you think about the probability and impact matrix question?
upvoted 0 times
...