PMI Exam PMI-100 Topic 2 Question 79 Discussion

Actual exam question for PMI's PMI-100 exam
Question #: 79
Topic #: 2
[All PMI-100 Questions]

When cost variance is negative and schedule variance is positive, the project is:

Show Suggested Answer Hide Answer
Suggested Answer: B

Contribute your Thoughts:

Daryl
9 months ago
I think the correct answer is A, because being under budget is a bigger concern than being behind schedule.
upvoted 0 times
...
Tonette
10 months ago
But positive schedule variance means we are ahead of schedule, so it's a bit confusing.
upvoted 0 times
...
Helga
10 months ago
I agree with Angelyn, negative cost variance means we are spending less than planned.
upvoted 0 times
...
Angelyn
10 months ago
A) under budget and behind schedule.
upvoted 0 times
...
Tomas
10 months ago
I think the correct answer is A, because being under budget is a bigger concern than being behind schedule.
upvoted 0 times
...
Shenika
10 months ago
This question is like a bad dad joke. 'When cost variance is negative and schedule variance is positive, the project is... behind schedule and over budget, of course!' *chuckles*
upvoted 0 times
Rebecka
9 months ago
D) complete; all planned values have been earned.
upvoted 0 times
...
Lucy
9 months ago
C) on schedule.
upvoted 0 times
...
Ethan
9 months ago
B) over budget and ahead of schedule.
upvoted 0 times
...
Micah
10 months ago
A) under budget and behind schedule.
upvoted 0 times
...
...
Lachelle
10 months ago
But positive schedule variance means we are ahead of schedule, so it's a bit confusing.
upvoted 0 times
...
Hector
10 months ago
I agree with Wai, negative cost variance means we are spending less than planned.
upvoted 0 times
...
Ardella
10 months ago
Complete? All planned values earned? No way, this project sounds like a hot mess. I'm going with B, the only logical answer here.
upvoted 0 times
Olga
9 months ago
Yeah, definitely over budget but at least ahead of schedule.
upvoted 0 times
...
Cecilia
10 months ago
I agree, B seems like the most logical choice in this situation.
upvoted 0 times
...
...
Georgeanna
11 months ago
Wait, how can the project be on schedule if the cost is negative and the schedule is positive? That doesn't make sense. I'll go with A.
upvoted 0 times
...
Whitley
11 months ago
Aha! I got this one. When you're over budget but ahead of schedule, that's exactly what option B describes. Easy peasy.
upvoted 0 times
Sunshine
10 months ago
A: Yup, that's correct. It's important to keep an eye on both cost and schedule variances.
upvoted 0 times
...
Emmanuel
10 months ago
B: So, the project is progressing faster than planned but costing more than expected.
upvoted 0 times
...
Bev
10 months ago
A: B) over budget and ahead of schedule.
upvoted 0 times
...
...
Wai
11 months ago
A) under budget and behind schedule.
upvoted 0 times
...
Rebbecca
11 months ago
Hmm, this one's tricky. If the cost is under budget but the schedule is behind, that doesn't sound too good. I'm thinking B is the way to go.
upvoted 0 times
Carri
10 months ago
Exactly, it's important to keep track of both cost and schedule variances.
upvoted 0 times
...
Frank
10 months ago
So, it means the project is not going as planned.
upvoted 0 times
...
Trevor
10 months ago
Yeah, if the cost is over budget but the schedule is ahead, that makes sense.
upvoted 0 times
...
Leontine
10 months ago
I think B is correct too.
upvoted 0 times
...
...

Save Cancel
az-700  pass4success  az-104  200-301  200-201  cissp  350-401  350-201  350-501  350-601  350-801  350-901  az-720  az-305  pl-300  

Warning: Cannot modify header information - headers already sent by (output started at /pass.php:70) in /pass.php on line 77