Which of the following is a process goal relevant to the construction phase of a project?

Show Suggested Answer Hide Answer
Suggested Answer: C

Contribute your Thoughts:

Rozella
1 months ago
This question is a real 'construction zone' for the candidates, huh? 'Develop test strategy' is the only answer that won't leave them 'under construction'.
upvoted 0 times
Mel
15 hours ago
B) Explore scope
upvoted 0 times
...
Gracia
12 days ago
A) Prove architecture early
upvoted 0 times
...
...
Maile
1 months ago
I'm tempted to choose 'Prove architecture early', but that's more of a design phase activity. 'Develop test strategy' is the process goal that fits best here.
upvoted 0 times
Lashonda
19 days ago
I think 'Prove architecture early' is more for the design phase.
upvoted 0 times
...
...
Ira
2 months ago
Ah, 'Form team' is a good one, but it's more of an organizational goal, not a process goal. 'Develop test strategy' is the way to go.
upvoted 0 times
Tula
1 months ago
I agree, it's important to have a solid plan in place for testing.
upvoted 0 times
...
Camellia
2 months ago
I think 'Develop test strategy' is crucial for the construction phase.
upvoted 0 times
...
...
Roy
2 months ago
I see your point, Geoffrey. But I think D) Form team is also important for successful project execution.
upvoted 0 times
...
Huey
2 months ago
Hmm, 'Explore scope' seems more like a goal for the planning phase, not construction. I'll go with 'Develop test strategy'.
upvoted 0 times
Rikki
1 months ago
Yeah, 'Prove architecture early' might be more relevant to the design phase.
upvoted 0 times
...
Cassi
1 months ago
I would also go with 'Develop test strategy' for the construction phase.
upvoted 0 times
...
Delmy
2 months ago
I agree, it's important to have a solid test strategy in place during construction.
upvoted 0 times
...
Katheryn
2 months ago
I think 'Develop test strategy' is a good choice for the construction phase.
upvoted 0 times
...
...
Maybelle
2 months ago
I think 'Develop test strategy' is the correct answer. It's a key process goal during the construction phase to ensure the project quality.
upvoted 0 times
...
Geoffrey
2 months ago
I disagree, I believe it's B) Explore scope because defining the project's boundaries is crucial.
upvoted 0 times
...
Launa
2 months ago
I think the answer is A) Prove architecture early.
upvoted 0 times
...

Save Cancel
az-700  pass4success  az-104  200-301  200-201  cissp  350-401  350-201  350-501  350-601  350-801  350-901  az-720  az-305  pl-300  

Warning: Cannot modify header information - headers already sent by (output started at /pass.php:70) in /pass.php on line 77