Deal of The Day! Hurry Up, Grab the Special Discount - Save 25% - Ends In 00:00:00 Coupon code: SAVE25
Welcome to Pass4Success

- Free Preparation Discussions

PMI Exam CAPM Topic 1 Question 96 Discussion

Actual exam question for PMI's CAPM exam
Question #: 96
Topic #: 1
[All CAPM Questions]

Which of the following are three inputs to the risk register?

Show Suggested Answer Hide Answer
Suggested Answer: C

Contribute your Thoughts:

Corrie
1 days ago
I see your point, Deeanna. It's important to consider all the options before making a final decision.
upvoted 0 times
...
Deeanna
4 days ago
I'm not sure, but I think D) Project scope statement, organizational process assets, and scope baseline could also be inputs to the risk register.
upvoted 0 times
...
Bethanie
8 days ago
I disagree, I believe the correct answer is C) Risk management plan, activity cost estimates, and project documents.
upvoted 0 times
...
Corrie
18 days ago
I think the answer is A) Risk register updates, stakeholder register, and quality management plan.
upvoted 0 times
...
Afton
23 days ago
Haha, this is a tricky one! I'm going to go with D just to see if I can throw the grader off.
upvoted 0 times
...
Derick
1 months ago
I'm not sure about that. I think B might be the right answer, with the communication management plan, enterprise environmental factors, and activity duration estimates.
upvoted 0 times
...
Junita
2 months ago
I think the correct answer is C. The risk management plan, activity cost estimates, and project documents are the inputs to the risk register.
upvoted 0 times
Leonor
24 days ago
That makes sense. Those inputs are crucial for identifying and analyzing risks.
upvoted 0 times
...
Maryln
28 days ago
The risk management plan, activity cost estimates, and project documents are the inputs to the risk register.
upvoted 0 times
...
Olive
1 months ago
I think the correct answer is C.
upvoted 0 times
...
Yasuko
1 months ago
Great job! It's important to understand the inputs to the risk register for effective project management.
upvoted 0 times
...
My
1 months ago
Yes, you are right. The risk management plan, activity cost estimates, and project documents are indeed inputs to the risk register.
upvoted 0 times
...
Bernardo
1 months ago
I think the correct answer is C.
upvoted 0 times
...
...

Save Cancel
az-700  pass4success  az-104  200-301  200-201  cissp  350-401  350-201  350-501  350-601  350-801  350-901  az-720  az-305  pl-300  

Warning: Cannot modify header information - headers already sent by (output started at /pass.php:70) in /pass.php on line 77