PECB Exam ISO-9001-Lead-Auditor Topic 5 Question 16 Discussion

Actual exam question for PECB's ISO-9001-Lead-Auditor exam
Question #: 16
Topic #: 5
[All ISO-9001-Lead-Auditor Questions]

A Health Trust has contracted with Servitup, a catering services organisation which has been certified to ISO 9001 for 1 year. It provides services to ten, small rural

hospitals in remote locations involving purchase and storage of dry goods and fresh produce, preparing meals and loading heated trolleys for ward service by hospital

staff. An auditor is conducting the first sole surveillance audit at one site with the Deputy Catering Manager (DCM).

At the closing meeting attended solely by the DCM, the auditor informs him that he has found numerous gaps in the QMS processes which lead him to consider

recommending suspension of the organisation's certification. He is particularly concerned with the evidence that patient health is being adversely affected by produce

stored beyond its safe consumption date, poor kitchen hygiene and undercooked meals. The DCM says that he cannot make any decisions about these issues in the

absence of the Catering Manager due to illness but will write everything down and report to the Catering Manager.

Which two actions should you take in the context of the audit?

Show Suggested Answer Hide Answer
Suggested Answer: B

Contribute your Thoughts:

Eladia
13 days ago
This is a classic case of 'buck-passing' at its finest. The DCM should have the authority to address these critical issues, especially when patient health is at stake.
upvoted 0 times
...
Anabel
28 days ago
You know, if they're serving undercooked meals, maybe the auditor should have sampled the food. I bet it was a little 'rare'.
upvoted 0 times
Fletcher
22 days ago
The auditor should have sampled the food.
upvoted 0 times
...
...
Kenda
1 months ago
Wait, the Catering Manager is out sick? This sounds like a perfect opportunity for the DCM to step up and take responsibility. I hope he doesn't pull a 'let me check with my boss' move.
upvoted 0 times
Myrtie
26 days ago
B) Call the individual(s) managing the audit programme to explain the situation and recommend immediate suspension of certification to protect the integrity of the Certification Body.
upvoted 0 times
...
...
Venita
1 months ago
Yes, that seems like the most appropriate action to take in this situation.
upvoted 0 times
...
Cordelia
1 months ago
I think we should call the audit programme managers and recommend suspension of certification.
upvoted 0 times
...
Jeannetta
1 months ago
I agree, the auditor should present the full report and give the organization a reasonable timeframe to implement corrective actions. Rushing to suspend the certification could do more harm than good.
upvoted 0 times
Nicholle
22 days ago
F) Thank the DCM for his time and express an expectation that improvements will be made in the QMS.
upvoted 0 times
...
Alaine
26 days ago
C) Continue with the meeting, present the audit conclusions and inform the DCM that the organisation will receive the audit report in due course.
upvoted 0 times
...
...
Roosevelt
2 months ago
The auditor's findings are concerning, but suspending the certification immediately seems a bit harsh. Shouldn't we give them a chance to address the issues first?
upvoted 0 times
Janet
5 days ago
C: E: Recommend that all personnel should be given urgent in-depth training in the QMS.
upvoted 0 times
...
Sanjuana
8 days ago
B: The auditor's findings are serious, patient health is at risk. Immediate action is necessary.
upvoted 0 times
...
Alexis
23 days ago
A: Call the individual(s) managing the audit programme to explain the situation and recommend immediate suspension of certification to protect the integrity of the Certification Body.
upvoted 0 times
...
...
Venita
2 months ago
We really need to address these issues to ensure patient safety.
upvoted 0 times
...

Save Cancel
az-700  pass4success  az-104  200-301  200-201  cissp  350-401  350-201  350-501  350-601  350-801  350-901  az-720  az-305  pl-300  

Warning: Cannot modify header information - headers already sent by (output started at /pass.php:70) in /pass.php on line 77
a