Select the best business practice for a supplier that is being newly added to the Approved Supplier List.

Show Suggested Answer Hide Answer
Suggested Answer: A, E

Contribute your Thoughts:

Dante
2 days ago
D all the way! Schedule confirmation is essential, and who needs sourcing when you've got that sweet manufacturer access? *taps forehead knowingly*
upvoted 0 times
...
Hoa
17 days ago
I'm going with C. Manufacturer link is key, and sourcing is more important than schedule confirmation. Gotta keep those suppliers on a tight leash!
upvoted 0 times
...
Fletcher
21 days ago
Hmm, this is a tricky one. I'd say option B looks like the best choice - let's them approve POs, source and confirm schedules, but not give them manufacturer access. Keeps things secure, right?
upvoted 0 times
Eleonore
3 days ago
I think option A might be better, it includes all the necessary steps for a supplier.
upvoted 0 times
...
Milly
6 days ago
I agree, option B seems like the most secure choice.
upvoted 0 times
...
...
Noel
21 days ago
That's a good point, having Manufacturer Link can improve transparency and communication with the supplier.
upvoted 0 times
...
Whitney
22 days ago
I disagree, I believe option C is better because it includes Manufacturer Link.
upvoted 0 times
...
Noel
23 days ago
I think the best business practice is option A.
upvoted 0 times
...

Save Cancel
az-700  pass4success  az-104  200-301  200-201  cissp  350-401  350-201  350-501  350-601  350-801  350-901  az-720  az-305  pl-300  

Warning: Cannot modify header information - headers already sent by (output started at /pass.php:70) in /pass.php on line 77