Identify the TWO activities performed in a negotiation by Category Manager after awarding

supplier:

Show Suggested Answer Hide Answer
Suggested Answer: A, D

Contribute your Thoughts:

Valentine
1 months ago
Is this a trick question? I bet the answer is A) Complete the award and B) Submit award for approval. Gotta dot all the i's and cross all the t's, am I right?
upvoted 0 times
...
Xochitl
1 months ago
Oof, tricky one. I'm going to go with C) Create contract and D) Close the negotiation. Seems like the natural next steps after awarding the supplier. Fingers crossed!
upvoted 0 times
Gregoria
8 days ago
Yes, closing the negotiation is also important to finalize the deal.
upvoted 0 times
...
Launa
21 days ago
I think you're right, creating the contract is definitely one of the activities.
upvoted 0 times
...
...
Gerald
1 months ago
Ha! This question is a real negotiation minefield. I bet the answer is B) Submit award for approval and D) Close the negotiation. Gotta get that boss' stamp of approval, you know?
upvoted 0 times
Santos
12 days ago
It's all about following the process and getting everything finalized.
upvoted 0 times
...
Catalina
13 days ago
After that, we can close the negotiation and move on to the next steps.
upvoted 0 times
...
Emogene
15 days ago
I think you're right, we definitely need to submit the award for approval first.
upvoted 0 times
...
...
Alfreda
2 months ago
Hmm, I'm not sure about this one. I was thinking it might be A) Complete the award and B) Submit award for approval. Doesn't the Category Manager have to finalize the award and get it approved before moving on?
upvoted 0 times
Ronny
8 days ago
So the correct activities are A) Complete the award and B) Submit award for approval.
upvoted 0 times
...
Arlen
9 days ago
After that, they can create the contract and close the negotiation.
upvoted 0 times
...
Rachael
11 days ago
Markus: So, after that, the negotiation can be closed, right?
upvoted 0 times
...
Markus
12 days ago
User 2: Yes, that's correct. Those are the two activities that need to be performed after awarding the supplier.
upvoted 0 times
...
Gussie
19 days ago
User 1: I think you're right, the Category Manager needs to complete the award and submit it for approval.
upvoted 0 times
...
Daniel
26 days ago
Yes, you're correct. The Category Manager needs to complete the award and submit it for approval.
upvoted 0 times
...
...
Alysa
2 months ago
I believe the correct activities are A) Complete the award and D) Close the negotiation. Once the award is given, the negotiation should be officially closed.
upvoted 0 times
...
Latia
2 months ago
I agree with Germaine. After awarding the supplier, the Category Manager needs to finalize the award and draft the contract.
upvoted 0 times
...
Haydee
2 months ago
I think the correct answer is C) Create contract and D) Close the negotiation. The Category Manager's job doesn't end with just awarding the supplier - they need to follow through with the contract and officially close the negotiation process.
upvoted 0 times
Susana
2 months ago
Yes, and they also have to close the negotiation to ensure everything is finalized.
upvoted 0 times
...
Paola
2 months ago
I agree, the Category Manager needs to create the contract to formalize the agreement.
upvoted 0 times
...
...
Germaine
3 months ago
I think the two activities are A) Complete the award and C) Create contract.
upvoted 0 times
...

Save Cancel
az-700  pass4success  az-104  200-301  200-201  cissp  350-401  350-201  350-501  350-601  350-801  350-901  az-720  az-305  pl-300  

Warning: Cannot modify header information - headers already sent by (output started at /pass.php:70) in /pass.php on line 77