You have a billable project for which the following details are provided:
Associated Inception-To-Date (ITD) Project Actual Cost: USD 60
Associated Project Budgeted Cost: USD 300
Contract Amount: USD 1000
Project Funded Amount: USD 750
Sum of Existing Revenue Events: USD 80
Identify the Associated Project Spent revenue that will get generated based on the preceding details. (Choose the best answer.)
Associated Project Percent Spent Example
The following formula calculates the percent spent revenue for the associated project.
((Sum of ITD Actual Cost for every subtask that is part of the associated task / Sum of Total Budgeted cost for every task that is part of associated task)
x Associated Project Funded Amount) -- Sum of Existing Invoice Event Amounts for the Associated Project
((60/300) x 750) -- 80 = 70
((Actual Cost / Budgeted Cost) x Budgeted Revenue) -- Sum of Revenue Event Amount
Telma
2 months agoMerilyn
12 days agoFrederic
1 months agoDorthy
1 months agoBrice
1 months agoAmos
2 months agoDiane
28 days agoValentine
1 months agoAdaline
2 months agoBilly
2 months agoWillow
13 days agoRoy
14 days agoHorace
15 days agoTimothy
16 days agoDottie
24 days agoRhea
1 months agoAnnamaria
2 months agoViola
2 months agoCory
3 months agoMalinda
3 months agoDominque
3 months agoIsabelle
3 months agoKarl
3 months agoInes
2 months agoJose
2 months agoEladia
2 months agoIola
2 months agoCammy
2 months agoFreeman
2 months ago