Oracle Exam 1Z0-1057-24 Topic 1 Question 7 Discussion

Actual exam question for Oracle's 1Z0-1057-24 exam
Question #: 7
Topic #: 1
[All 1Z0-1057-24 Questions]

You have a billable project for which the following details are provided:

Associated Inception-To-Date (ITD) Project Actual Cost: USD 60

Associated Project Budgeted Cost: USD 300

Contract Amount: USD 1000

Project Funded Amount: USD 750

Sum of Existing Revenue Events: USD 80

Identify the Associated Project Spent revenue that will get generated based on the preceding details. (Choose the best answer.)

Show Suggested Answer Hide Answer
Suggested Answer: D

Ref: https://docs.oracle.com/en/cloud/saas/project-portfolio-management/19b/oapjb/manage-project-contract-revenue.html#OAPJB164173

Associated Project Percent Spent Example

The following formula calculates the percent spent revenue for the associated project.

((Sum of ITD Actual Cost for every subtask that is part of the associated task / Sum of Total Budgeted cost for every task that is part of associated task)

x Associated Project Funded Amount) -- Sum of Existing Invoice Event Amounts for the Associated Project

((60/300) x 750) -- 80 = 70

((Actual Cost / Budgeted Cost) x Budgeted Revenue) -- Sum of Revenue Event Amount


Contribute your Thoughts:

Telma
2 months ago
Wait, is this a trick question? I'm starting to second-guess myself now.
upvoted 0 times
Merilyn
12 days ago
You're on the right track. Keep going!
upvoted 0 times
...
Frederic
1 months ago
B) USD 120
upvoted 0 times
...
Dorthy
1 months ago
No, it's not a trick question. Just calculate based on the provided details.
upvoted 0 times
...
Brice
1 months ago
A) USD 184
upvoted 0 times
...
...
Amos
2 months ago
Hmm, let me see... Ah, I've got it! The answer is C) USD 134. I'm feeling pretty confident about this one.
upvoted 0 times
Diane
28 days ago
No, I believe the correct answer is C) USD 134.
upvoted 0 times
...
Valentine
1 months ago
I think the answer is A) USD 184.
upvoted 0 times
...
...
Adaline
2 months ago
I'm not sure, but I think USD 120 makes sense based on the information provided.
upvoted 0 times
...
Billy
2 months ago
This question is a real head-scratcher. I feel like I need to break out my calculator and a spreadsheet to figure this one out.
upvoted 0 times
Willow
13 days ago
Hmm, I'm not sure. Maybe it's USD 70.
upvoted 0 times
...
Roy
14 days ago
Actually, I'm pretty sure it's USD 184.
upvoted 0 times
...
Horace
15 days ago
No, I believe it's USD 134.
upvoted 0 times
...
Timothy
16 days ago
I think the answer is USD 120.
upvoted 0 times
...
Dottie
24 days ago
I'm not sure, maybe it's B) USD 120
upvoted 0 times
...
Rhea
1 months ago
B) USD 120
upvoted 0 times
...
Annamaria
2 months ago
I think the answer is A) USD 184
upvoted 0 times
...
Viola
2 months ago
A) USD 184
upvoted 0 times
...
...
Cory
3 months ago
I agree with Karl's logic. The calculations make sense to me.
upvoted 0 times
...
Malinda
3 months ago
I believe the answer is USD 120 because it takes into account the project actual cost and budgeted cost.
upvoted 0 times
...
Dominque
3 months ago
I agree with Isabelle, USD 120 seems to be the correct answer.
upvoted 0 times
...
Isabelle
3 months ago
I think the answer is USD 120.
upvoted 0 times
...
Karl
3 months ago
The correct answer is C) USD 134. This is calculated by taking the Project Funded Amount of USD 750 and subtracting the Sum of Existing Revenue Events of USD 80, which leaves USD 670. The Associated Project Spent revenue is then calculated as 670/1000 * 300 = USD 134.
upvoted 0 times
Ines
2 months ago
Oh, I see. Thanks for clarifying!
upvoted 0 times
...
Jose
2 months ago
Great, thanks for clarifying!
upvoted 0 times
...
Eladia
2 months ago
Actually, the correct answer is C) USD 134.
upvoted 0 times
...
Iola
2 months ago
That makes sense, the calculation adds up.
upvoted 0 times
...
Cammy
2 months ago
I think the answer is A) USD 184.
upvoted 0 times
...
Freeman
2 months ago
I think the answer is C) USD 134.
upvoted 0 times
...
...