Deal of The Day! Hurry Up, Grab the Special Discount - Save 25% - Ends In 00:00:00 Coupon code: SAVE25
Welcome to Pass4Success

- Free Preparation Discussions

Oracle Exam 1Z0-1057-24 Topic 1 Question 7 Discussion

Actual exam question for Oracle's 1Z0-1057-24 exam
Question #: 7
Topic #: 1
[All 1Z0-1057-24 Questions]

You have a billable project for which the following details are provided:

Associated Inception-To-Date (ITD) Project Actual Cost: USD 60

Associated Project Budgeted Cost: USD 300

Contract Amount: USD 1000

Project Funded Amount: USD 750

Sum of Existing Revenue Events: USD 80

Identify the Associated Project Spent revenue that will get generated based on the preceding details. (Choose the best answer.)

Show Suggested Answer Hide Answer
Suggested Answer: D

Ref: https://docs.oracle.com/en/cloud/saas/project-portfolio-management/19b/oapjb/manage-project-contract-revenue.html#OAPJB164173

Associated Project Percent Spent Example

The following formula calculates the percent spent revenue for the associated project.

((Sum of ITD Actual Cost for every subtask that is part of the associated task / Sum of Total Budgeted cost for every task that is part of associated task)

x Associated Project Funded Amount) -- Sum of Existing Invoice Event Amounts for the Associated Project

((60/300) x 750) -- 80 = 70

((Actual Cost / Budgeted Cost) x Budgeted Revenue) -- Sum of Revenue Event Amount


Contribute your Thoughts:

Telma
9 days ago
Wait, is this a trick question? I'm starting to second-guess myself now.
upvoted 0 times
...
Amos
11 days ago
Hmm, let me see... Ah, I've got it! The answer is C) USD 134. I'm feeling pretty confident about this one.
upvoted 0 times
...
Adaline
22 days ago
I'm not sure, but I think USD 120 makes sense based on the information provided.
upvoted 0 times
...
Billy
22 days ago
This question is a real head-scratcher. I feel like I need to break out my calculator and a spreadsheet to figure this one out.
upvoted 0 times
Viola
5 days ago
A) USD 184
upvoted 0 times
...
...
Cory
25 days ago
I agree with Karl's logic. The calculations make sense to me.
upvoted 0 times
...
Malinda
26 days ago
I believe the answer is USD 120 because it takes into account the project actual cost and budgeted cost.
upvoted 0 times
...
Dominque
29 days ago
I agree with Isabelle, USD 120 seems to be the correct answer.
upvoted 0 times
...
Isabelle
1 months ago
I think the answer is USD 120.
upvoted 0 times
...
Karl
1 months ago
The correct answer is C) USD 134. This is calculated by taking the Project Funded Amount of USD 750 and subtracting the Sum of Existing Revenue Events of USD 80, which leaves USD 670. The Associated Project Spent revenue is then calculated as 670/1000 * 300 = USD 134.
upvoted 0 times
Jose
9 days ago
Great, thanks for clarifying!
upvoted 0 times
...
Eladia
9 days ago
Actually, the correct answer is C) USD 134.
upvoted 0 times
...
Iola
12 days ago
That makes sense, the calculation adds up.
upvoted 0 times
...
Cammy
15 days ago
I think the answer is A) USD 184.
upvoted 0 times
...
Freeman
22 days ago
I think the answer is C) USD 134.
upvoted 0 times
...
...

Save Cancel
az-700  pass4success  az-104  200-301  200-201  cissp  350-401  350-201  350-501  350-601  350-801  350-901  az-720  az-305  pl-300  

Warning: Cannot modify header information - headers already sent by (output started at /pass.php:70) in /pass.php on line 77