You have a billable project for which the following details are provided:
Associated Inception-To-Date (ITD) Project Actual Cost: USD 60
Associated Project Budgeted Cost: USD 300
Contract Amount: USD 1000
Project Funded Amount: USD 750
Sum of Existing Revenue Events: USD 80
Identify the Associated Project Spent revenue that will get generated based on the preceding details. (Choose the best answer.)
Associated Project Percent Spent Example
The following formula calculates the percent spent revenue for the associated project.
((Sum of ITD Actual Cost for every subtask that is part of the associated task / Sum of Total Budgeted cost for every task that is part of associated task)
x Associated Project Funded Amount) -- Sum of Existing Invoice Event Amounts for the Associated Project
((60/300) x 750) -- 80 = 70
((Actual Cost / Budgeted Cost) x Budgeted Revenue) -- Sum of Revenue Event Amount
Telma
9 days agoAmos
11 days agoAdaline
22 days agoBilly
22 days agoViola
5 days agoCory
25 days agoMalinda
26 days agoDominque
29 days agoIsabelle
1 months agoKarl
1 months agoJose
9 days agoEladia
9 days agoIola
12 days agoCammy
15 days agoFreeman
22 days ago