Microsoft Exam MB-330 Topic 4 Question 95 Discussion

Actual exam question for Microsoft's MB-330 exam
Question #: 95
Topic #: 4
[All MB-330 Questions]

A company needs to be alerted when the calculated planned cost of a bill of materials (BOM) product is older than 30 days.

You need to configure the number of days validation in the system.

Where should you specify the number of days?

Select only one answer.

Show Suggested Answer Hide Answer
Suggested Answer: A

Contribute your Thoughts:

Florinda
1 months ago
This is a trick question. The real answer is F) Voodoo magic. Just wave a chicken bone over the system and it'll sort itself out.
upvoted 0 times
Twanna
6 days ago
C) Inventory and warehouse management parameters
upvoted 0 times
...
...
Carla
2 months ago
Definitely E) Released product. I mean, if the cost is older than 30 days, the product is basically expired, right? Time to release the new and improved version!
upvoted 0 times
Peggie
7 days ago
Yeah, that seems like the most logical place to configure it.
upvoted 0 times
...
Veronique
20 days ago
I agree, it makes sense to specify the number of days there.
upvoted 0 times
...
Buffy
1 months ago
I think C) Inventory and warehouse management parameters is the right choice.
upvoted 0 times
...
...
Devorah
2 months ago
I'm going to go with B) Stop explosion. Sounds like the kind of thing you'd want to stop, you know? Exploding BOMs, not good.
upvoted 0 times
Walton
13 days ago
I'm not sure, but I think D) BOM calculation groups might be the correct answer.
upvoted 0 times
...
Laurena
1 months ago
I agree, C) Inventory and warehouse management parameters seems like the best option.
upvoted 0 times
...
Alline
1 months ago
I think C) Inventory and warehouse management parameters is the right choice.
upvoted 0 times
...
...
Rickie
2 months ago
Hmm, I'm not so sure. Maybe it's D) BOM calculation groups? Seems like the natural place to set that kind of validation.
upvoted 0 times
Sheldon
16 days ago
I agree with you, D) BOM calculation groups seems like the right choice.
upvoted 0 times
...
Yesenia
1 months ago
I'm leaning towards A) Cost price model.
upvoted 0 times
...
Arlean
1 months ago
I believe it's E) Released product.
upvoted 0 times
...
Sue
2 months ago
I think it might be C) Inventory and warehouse management parameters.
upvoted 0 times
...
...
Tuyet
2 months ago
I think it's C) Inventory and warehouse management parameters. That's where you'd configure the number of days for the BOM cost validation, right?
upvoted 0 times
Kayleigh
2 months ago
I believe it's D) BOM calculation groups. That's where you set up the validation for the planned cost of a BOM product, isn't it?
upvoted 0 times
...
Bernardine
2 months ago
Yes, you are correct. The number of days for the BOM cost validation is specified in Inventory and warehouse management parameters.
upvoted 0 times
...
...
Talia
2 months ago
I believe it should be in BOM calculation groups, as that's where you define how BOMs are calculated.
upvoted 0 times
...
Arthur
3 months ago
I agree with Melodie, because that's where you can set global settings for inventory management.
upvoted 0 times
...
Melodie
3 months ago
I think the number of days should be specified in Inventory and warehouse management parameters.
upvoted 0 times
...