A company classifies items as A, B, C, and D for planning purposes.
You run Planning Optimization for the C items with the following setup:
* a plan filter for the A, B, and D items
* a runtime filter for the C items
The Planning Optimization output does not create any planned orders.
You need to produce results in Planning Optimization for the C items without affecting the A, B, and D items.
What should you do?
Select only one answer.