ISTQB Exam CT-TAE Topic 3 Question 48 Discussion

Actual exam question for ISTQB's CT-TAE exam
Question #: 48
Topic #: 3
[All CT-TAE Questions]

A regression test suite consist of 500 test cases which are all executed manually. The business case for a pilot project is based on the adoption of test automation using a commercial tool that will reduce the execution time by a factor of 90% for 100% of the tests in the regression test suite. The pilot project lasted one month ( as planned) and you are currently its results. At the end of the pilot project, 40% of the regression tests have been automated and their execution time has been reduce by 60%.

Which of the following statements is TRUE in this scenario?

Show Suggested Answer Hide Answer
Suggested Answer: A

Contribute your Thoughts:

Galen
2 months ago
I think the pilot project duration of one month was fine. They got some good results, even if not the full target. Now they can use that as a baseline to plan the next phase more realistically.
upvoted 0 times
Tarra
10 days ago
They can learn from this pilot project and adjust their approach for better results.
upvoted 0 times
...
Emmett
16 days ago
Yeah, they should aim for achievable goals in the next phase.
upvoted 0 times
...
Lonna
23 days ago
I think they should have set a more realistic target for automation.
upvoted 0 times
...
Salena
28 days ago
I agree, one month was enough to see some progress.
upvoted 0 times
...
Kenneth
1 months ago
B: The target defined for the business case seems difficult to hit -- it should be realistic.
upvoted 0 times
...
Latanya
1 months ago
A: The duration of the pilot project was too short --it should last until the success factors are achieved.
upvoted 0 times
...
...
Ruthann
2 months ago
Haha, 'too accurate' as a critique? Sounds like someone's trying to make excuses for missing their targets. If you can't measure it, how do you know you achieved it?
upvoted 0 times
...
Sage
2 months ago
I agree, the target of 90% reduction in execution time for 100% of the tests seems overly ambitious. They should have set a more achievable goal, like 70-80% reduction for the initial 40-50% automation.
upvoted 0 times
...
Gary
2 months ago
Looks like the pilot project was a partial success. 40% automation with 60% reduction in execution time is not bad, but still far from the target. Definitely need to revisit the business case and make it more realistic.
upvoted 0 times
Juan
1 months ago
D: Agreed, we need to make sure we set realistic goals for future projects.
upvoted 0 times
...
Alverta
1 months ago
C: Maybe we should extend the pilot project to fully achieve the success factors.
upvoted 0 times
...
Lashaunda
1 months ago
B: Yeah, we definitely need to adjust our expectations and make sure they are achievable.
upvoted 0 times
...
Eva
1 months ago
A: The target defined for the business case seems difficult to hit -- it should be realistic
upvoted 0 times
...
...
Mabelle
2 months ago
But maybe the target defined for the business case was too accurate. It should be more flexible.
upvoted 0 times
...
Corazon
2 months ago
I agree with Lucy. The success factors should be achieved before ending the project.
upvoted 0 times
...
Lucy
2 months ago
I think the duration of the pilot project was too short.
upvoted 0 times
...

Save Cancel
az-700  pass4success  az-104  200-301  200-201  cissp  350-401  350-201  350-501  350-601  350-801  350-901  az-720  az-305  pl-300  

Warning: Cannot modify header information - headers already sent by (output started at /pass.php:70) in /pass.php on line 77