iSQI Exam CTAL-TM_Syll2012 Topic 3 Question 81 Discussion

Actual exam question for iSQI's CTAL-TM_Syll2012 exam
Question #: 81
Topic #: 3
[All CTAL-TM_Syll2012 Questions]

Which of the following statements, about the test reporting activities for a project adopting an iterative lifecycle model with very short iterations (e.g. two weeks iterations), is correct? K2 1 credit

Show Suggested Answer Hide Answer
Suggested Answer: D

Contribute your Thoughts:

Glen
3 days ago
Haha, imagine if we just said 'test reporting? Who needs that?' No, that's not how it works. Option D is the way to go, folks.
upvoted 0 times
...
Fernanda
6 days ago
I agree with Nilsa. Test reporting helps us stay on track and make informed decisions. It's not something we can just ignore.
upvoted 0 times
...
Maxima
13 days ago
I believe test reporting activities should be performed at the end of the last iteration.
upvoted 0 times
...
Nilsa
13 days ago
Option D is definitely the correct answer. Test reporting is crucial, even with short iterations. We need to review the results before moving on to the next sprint.
upvoted 0 times
...
Reta
19 days ago
I agree with Joanna. The reports can help in conducting post-iteration review sessions.
upvoted 0 times
...
Joanna
25 days ago
I think test reporting activities are still important with an iterative lifecycle.
upvoted 0 times
...