Deal of The Day! Hurry Up, Grab the Special Discount - Save 25% - Ends In 00:00:00 Coupon code: SAVE25
Welcome to Pass4Success

- Free Preparation Discussions

iSQI Exam CTAL-TM_Syll2012 Topic 3 Question 55 Discussion

Actual exam question for iSQI's CTAL-TM_Syll2012 exam
Question #: 55
Topic #: 3
[All CTAL-TM_Syll2012 Questions]

Based on the historical data of 5 past and similar projects, you have calculated these average numbers of defects detected in system testing.

- For each 10000 LOC (lines of code), 200 defects

- For each person-month of development team effort, 49 defects

You want to use this information to perform estimation for a new project.

The project manager tells you that he/she has estimated 20000 new LOC for this new project.

Four developers work for four months on this project before system testing.

During system testing, 797 defects are discovered.

Assume that the system test of this new project is using the same amount of work as spent in the past projects.

Based on this information only, which of the following statement is certainly true about this project? K3 3 credits

Show Suggested Answer Hide Answer
Suggested Answer: A, C, F

Contribute your Thoughts:

Minna
13 days ago
Hold on, did they just throw in a joke about the project manager's estimates? That's hilarious! As for the actual answer, I'm leaning towards option D as well. The numbers just don't add up otherwise.
upvoted 0 times
...
Cherelle
19 days ago
I'm not sure about this one. Option B seems plausible, but the question specifically says to base the answer on the information provided, and that doesn't mention anything about the number of defects being proportional to the development team effort.
upvoted 0 times
Gladis
3 days ago
Yeah, the question asks us to base our answer on the given information, so we need to consider that.
upvoted 0 times
...
Lamonica
6 days ago
I think option B is not necessarily true based on the information provided.
upvoted 0 times
...
...
Lawana
24 days ago
Hmm, this is a tricky one. Based on the information provided, I think option D is the correct answer. The number of defects found during system testing is much higher than what was expected, suggesting that more LOC than planned were delivered with a higher defect density.
upvoted 0 times
...
Clay
1 months ago
But the number of defects found during system testing is not proportional to the development team effort.
upvoted 0 times
...
Rebbeca
1 months ago
I disagree, I believe the answer is B.
upvoted 0 times
...
Clay
1 months ago
I think the answer is D.
upvoted 0 times
...

Save Cancel
az-700  pass4success  az-104  200-301  200-201  cissp  350-401  350-201  350-501  350-601  350-801  350-901  az-720  az-305  pl-300  

Warning: Cannot modify header information - headers already sent by (output started at /pass.php:70) in /pass.php on line 77
a