iSQI Exam CTAL-TM_Syll2012 Topic 3 Question 32 Discussion

Actual exam question for iSQI's CTAL-TM_Syll2012 exam
Question #: 32
Topic #: 3
[All CTAL-TM_Syll2012 Questions]

You are the Test Manager on a project following an iterative life-cycle model. The project should consist of nine iterations of one month duration each. It is planned to develop the most important features to have a stable core of the application in the first three iterations and to add the additional features in the last six iterations.

At the beginning of the first iteration, only a draft version of the requirements specification document for the core features is available. Assume that during each of the first three iterations, the chosen features are fully completed and unit tested.

Which of the following statements is true in this context?

K4 3 credits

Show Suggested Answer Hide Answer
Suggested Answer: C

Contribute your Thoughts:

Detra
2 months ago
Applying the same test strategy as used in a sequential life cycle model is not appropriate here. Iterative models require a more agile and continuous testing approach.
upvoted 0 times
Tequila
14 days ago
C) You should allocate all the effort for the system test phase only in the last iteration
upvoted 0 times
...
Kristine
1 months ago
B) You should allocate a large effort for system testing during the first three iterations
upvoted 0 times
...
Dona
1 months ago
A) The system test phase should start when all the requirements are frozen
upvoted 0 times
...
...
Polly
2 months ago
Allocating all the effort for the system test phase only in the last iteration is not a good idea. We should be testing the features as we build them, not waiting until the end.
upvoted 0 times
Heidy
6 days ago
Allocating all the effort for the system test phase only in the last iteration is not a good idea. We should be testing the features as we build them, not waiting until the end.
upvoted 0 times
...
Susana
7 days ago
B) You should allocate a large effort for system testing during the first three iterations
upvoted 0 times
...
Lamonica
9 days ago
A) The system test phase should start when all the requirements are frozen
upvoted 0 times
...
...
Callie
2 months ago
I bet the test manager is still using a flip phone and a typewriter. Welcome to the 21st century, my friend!
upvoted 0 times
Rose
4 days ago
D) You should apply the same test strategy as used in a sequential life cycle model
upvoted 0 times
...
Cecil
5 days ago
C) You should allocate all the effort for the system test phase only in the last iteration
upvoted 0 times
...
Kyoko
26 days ago
B) You should allocate a large effort for system testing during the first three iterations
upvoted 0 times
...
Jean
1 months ago
A) The system test phase should start when all the requirements are frozen
upvoted 0 times
...
...
Pearlie
2 months ago
But shouldn't we allocate some effort for system testing during the first three iterations as well?
upvoted 0 times
...
Glory
2 months ago
I agree with Detra, it's important to have stable core features before moving to system testing.
upvoted 0 times
...
Dorathy
2 months ago
This question is a real head-scratcher. I wonder if the test manager has ever heard of the concept of 'testing early and often'?
upvoted 0 times
Kate
1 months ago
B) You should allocate a large effort for system testing during the first three iterations
upvoted 0 times
...
Roxanne
2 months ago
A) The system test phase should start when all the requirements are frozen
upvoted 0 times
...
...
Detra
2 months ago
I think we should start system testing when all requirements are frozen.
upvoted 0 times
...

Save Cancel
az-700  pass4success  az-104  200-301  200-201  cissp  350-401  350-201  350-501  350-601  350-801  350-901  az-720  az-305  pl-300  

Warning: Cannot modify header information - headers already sent by (output started at /pass.php:70) in /pass.php on line 77