Which of the following appropriate tasks for the Test Analyst is performed during the test analysis phase?
The correct answer is B. The acceptance criteria are not testable.
The acceptance criteria are not testable
Reference =
ISTQB Test Analyst Syllabus and Study Guide3, Section 2.1.1 Test Analyst Tasks in the Test Process
What is User Story and Acceptance Criteria (Examples)4, Section 2. What is Acceptance Criteria?