Over the past 90 days, a buying company's manufacturing engineers have reported an increase in the number of defective parts received from a key supplier. The engineers report that there are three different types of defects occurring, and that they are all being discovered during production. The supplier states that it does not have enough resources to assess the root cause of the three types of defects all at one time. Which of the following should the buying firm do in this instance?
Working with engineering to assess the impact of each defect type on customers helps prioritize corrective actions effectively. Addressing the defect with the highest customer impact first ensures that resources are focused on the most critical issues, improving product quality and customer satisfaction.