ISM Exam CPSM1 Topic 2 Question 91 Discussion

Actual exam question for ISM's CPSM1 exam
Question #: 91
Topic #: 2
[All CPSM1 Questions]

A project manager is assigned to a project, either full-time or part-time, depending onthe size of the project, and then must negotiate for the services of individual teammembers with each appropriate functional manager in:

Show Suggested Answer Hide Answer
Suggested Answer: A

Contribute your Thoughts:

Hubert
29 days ago
D) Control Organization? Is that like a secret spy agency for project managers? I'm in! Do we get cool code names and invisible cars, or is that just in the movies?
upvoted 0 times
...
Melodie
1 months ago
C) Project Organization, all the way! No more fighting over resources, the project manager has full control. Although, I hear the catering budget is a bit tight in those setups.
upvoted 0 times
Lore
12 days ago
A) Functional Organization
upvoted 0 times
...
...
Katie
1 months ago
A) Functional Organization? Really? Where's the challenge? I want to see the project manager wheeling and dealing in a Matrix Organization. That's where the real action is!
upvoted 0 times
Sylvie
3 days ago
I agree, the Matrix Organization definitely adds a layer of complexity to the negotiation process.
upvoted 0 times
...
...
Solange
2 months ago
I'm not sure, but I think C) Project Organization could also be a possibility. Project managers are assigned to projects in project organizations.
upvoted 0 times
...
Marti
2 months ago
I agree with Suzi. In a matrix organization, project managers negotiate for team members with functional managers.
upvoted 0 times
...
Vinnie
2 months ago
B) Matrix Organization, definitely! That's where the project manager has to navigate the complex web of functional and project responsibilities. I can already feel the headache coming on just thinking about it.
upvoted 0 times
Eric
1 months ago
C) Project Organization
upvoted 0 times
...
Kimi
1 months ago
B) Matrix Organization
upvoted 0 times
...
Novella
2 months ago
A) Functional Organization
upvoted 0 times
...
...
Suzi
3 months ago
I think the answer is B) Matrix Organization.
upvoted 0 times
...

Save Cancel
az-700  pass4success  az-104  200-301  200-201  cissp  350-401  350-201  350-501  350-601  350-801  350-901  az-720  az-305  pl-300  

Warning: Cannot modify header information - headers already sent by (output started at /pass.php:70) in /pass.php on line 77