ISM Exam CPSM1 Topic 1 Question 104 Discussion

Actual exam question for ISM's CPSM1 exam
Question #: 104
Topic #: 1
[All CPSM1 Questions]

What provides an illustration of the project's scope sand all tasks become the basicfor monitoring the project's progress?

Show Suggested Answer Hide Answer
Suggested Answer: D

Contribute your Thoughts:

Pansy
11 days ago
Is the work breakdown structure the answer? I hope so, otherwise I'll be breaking down in tears during the exam.
upvoted 0 times
...
Artie
25 days ago
A work breakdown structure? More like a work breakdown masterpiece! That's the answer that's gonna get me that certification.
upvoted 0 times
Rolf
4 days ago
A) Work breakdown structure
upvoted 0 times
...
...
Erinn
1 months ago
Work breakdown structure all the way! It's like a project management superpower - you can see the whole project at a glance.
upvoted 0 times
Tegan
16 days ago
A) Work breakdown structure
upvoted 0 times
...
...
Mitzie
1 months ago
I'm going with A. The work breakdown structure is the key to keeping the project on track and ensuring nothing falls through the cracks.
upvoted 0 times
Fernanda
3 days ago
It definitely provides a clear illustration of the project's scope.
upvoted 0 times
...
Reiko
4 days ago
I think it helps to break down the project into manageable tasks.
upvoted 0 times
...
Glen
25 days ago
I agree, the work breakdown structure is essential for project monitoring.
upvoted 0 times
...
...
Jesusita
1 months ago
I'm not sure, but I think it's between A) and C).
upvoted 0 times
...
Arlette
2 months ago
The work breakdown structure is the obvious choice here. It's like a roadmap for the project, clearly laying out all the tasks and milestones.
upvoted 0 times
Kristofer
5 days ago
B) Progress structure
upvoted 0 times
...
Malcolm
8 days ago
Yes, the work breakdown structure is essential for monitoring the project's progress.
upvoted 0 times
...
Felice
16 days ago
A) Work breakdown structure
upvoted 0 times
...
...
Hailey
2 months ago
I agree with Ardella, the work breakdown structure helps define the project scope.
upvoted 0 times
...
Ardella
2 months ago
I think the answer is A) Work breakdown structure.
upvoted 0 times
...

Save Cancel
az-700  pass4success  az-104  200-301  200-201  cissp  350-401  350-201  350-501  350-601  350-801  350-901  az-720  az-305  pl-300  

Warning: Cannot modify header information - headers already sent by (output started at /pass.php:70) in /pass.php on line 77
a